- Work Description
- EXISTING ATTACHED 2-CAR GARAGE TO BE CONVERTED TO AN ADU PER CA GOVT CODE 65852.2(E)(1)(A) & PER WFPP
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 12/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | STARR CHEN |
| Corrections Issued | 3/16/2020 | STARR CHEN |
| Quality Review Completed | 3/17/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 6/12/2020 | APPLICANT |
| Plan Check Approved | 5/7/2021 | STARR CHEN |
| Issued | 5/24/2021 | APPLICANT |
| Building Plans Picked Up | 5/25/2021 | APPLICANT |
| CofO in Progress | 11/20/2021 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/3/2021 | DEROLD HAUFF |
| CofO Issued | 12/3/2021 | DEROLD HAUFF |
| Permit Finaled | 12/3/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 4/9/2020 | STARR CHEN |
| Address approval | Cleared | 9/8/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 9/8/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/8/2020 | CECILIO NAVARRO |
| Community Plan Implem. Overlay | Cleared | 3/2/2021 | HELEN JADALI |
| Tenant Habitability Plan | Cleared | 4/28/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/15/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/16/2021 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 7/16/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/23/2021 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/23/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 7/23/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/23/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/30/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/30/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/30/2021 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 7/30/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 8/3/2021 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 8/10/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/10/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/12/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/12/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 10/12/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 10/12/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 10/12/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 10/21/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 10/21/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 11/12/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 11/18/2021 | OK to Issue CofO | JOAQUIN GREENOUGH |