10518 N REDMONT AVE 91042

Certificate Information: 10518 N REDMONT AVE 91042

Application / Permit
20016-10000-06024
Plan Check / Job No.
B20LA04072
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 8/18/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 FARSHAD ALIMOHAMADI
Corrections Issued 3/5/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/13/2020 CRISTINA SALAZAR
Applicant returned to address corrections 7/21/2020 ZAW HAN
Plan Check Approved 7/27/2020 ZAW HAN
Issued 8/18/2020 APPLICANT
Building Plans Picked Up 8/21/2020 APPLICANT
CofO in Progress 5/31/2023 WILLIAM WREN
Permit Finaled 6/5/2023 MICHAEL SMITH
CofO Issued 6/5/2023 MICHAEL SMITH
Permit Finaled 6/5/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/5/2020 JUAN ASHTON
CPC Cleared 3/5/2020 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 3/5/2020 JUAN ASHTON
Grading Pre-Inspection Cleared 3/5/2020 PATRICK MISCHLICH
Private sewage disp. approval Cleared 3/5/2020 PATRICK MISCHLICH
Sewer availability Cleared 3/5/2020 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/19/2021 Partial Approval MATTHEW NELSON
Deputy Drilled-In Anchors 9/23/2021 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 10/8/2021 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 10/8/2021 Not Ready for Inspection MATTHEW NELSON
Wood Frame 10/8/2021 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 10/19/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 10/19/2021 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 10/19/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 11/4/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/10/2022 Not Ready for Inspection GREGG CUMMINGS
Rough-Elec/Plmb/HVAC 3/10/2022 Corrections Issued GREGG CUMMINGS
Wood Frame 3/10/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 3/30/2022 Approved MATTHEW NELSON
Insulation 4/8/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 4/12/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/2/2022 Approved MATTHEW NELSON
Final 5/8/2023 Corrections Issued WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 5/8/2023 SGSOV Approved WILLIAM WREN
Smoke Detectors 5/8/2023 Approved WILLIAM WREN
Final 5/15/2023 OK to Issue CofO WILLIAM WREN