1590 W 36TH ST 90018
Certificate Information: 1590 W 36TH ST 90018
- Application / Permit
- 20016-10000-05808
- Plan Check / Job No.
- B20LA03892
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) detached garage into an Accessory Dwelling Unit. Detached ADU per ordinance.
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2020 | HELEN NGUYEN |
| Corrections Issued | 3/3/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/7/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/13/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/26/2020 | HELEN NGUYEN |
| Plan Check Approved | 6/8/2020 | HELEN NGUYEN |
| Building Plans Picked Up | 6/11/2020 | APPLICANT |
| Issued | 7/17/2020 | APPLICANT |
| CofO in Progress | 5/13/2021 | ROBERT MCDOWELL |
| CofO Issued | 9/2/2021 | DEROLD HAUFF |
| Permit Finaled | 9/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2020 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 3/4/2020 | JEREMY CARTER |
| Sewer availability | Cleared | 3/4/2020 | JUAN ASHTON |
| Address approval | Cleared | 5/18/2020 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/23/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Pre-Inspection | 11/24/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 1/15/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 2/19/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 2/19/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 2/19/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/8/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Final | 4/8/2021 | Conditional Approval | ROBERT MCDOWELL |
| HVAC-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| METHANE-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| METHANE-Rough | 4/8/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Final | 5/13/2021 | OK to Issue CofO | ROBERT MCDOWELL |