444 S FLOWER ST 44th Floor 90071

Certificate Information: 444 S FLOWER ST 44th Floor 90071

Application / Permit
20016-10000-05807
Plan Check / Job No.
B20LA03891
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
PROPOSED FULL FLOOR TI FOR OFFICE SPACE, DEMO, NEW NON-LOAD BEARING INTERIOR PARTITIONS, CEILINGS, MILLWORK, FINISHES AND RESTROOM UPGRADES; NO STRUCTURAL WORK
Permit Issued
Issued on 5/21/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 10/22/2020

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 SINA KHOSRAVI
Corrections Issued 2/27/2020 SINA KHOSRAVI
Plan Check Approved 4/27/2020 SHANGQIN XIE
Building Plans Picked Up 4/28/2020 APPLICANT
Issued 5/21/2020 LADBS
Permit Finaled 10/22/2020 KATY RAMIREZ

Permit Application Clearance Information

Fire Marshall Fire Life Safety Cleared 4/15/2020 OSCAR SALGADO JR

Contact Information

Architect Limahelu,, Frank Hendrik; Lic. No.: C14425 11509 ALBERS STREET      NORTH HOLLYWOOD, CA 91601
Contractor Hitt Contracting Inc; Lic. No.: 811478-B 251 LITTLE FALLS DRIVE      WILMINGTON, DE 19808

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 7/10/2020 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 7/29/2020 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 7/31/2020 Partial Inspection KATY RAMIREZ
Drywall Nailing 8/3/2020 Partial Approval KATY RAMIREZ
T-Bar Ceiling 8/20/2020 Partial Inspection KATY RAMIREZ
T-Bar Ceiling 8/24/2020 Partial Approval KATY RAMIREZ
Final 10/8/2020 Not Ready for Inspection DANIEL COLLINS
Green Building Final 10/8/2020 Not Ready for Inspection DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 10/8/2020 SGSOV Approved DANIEL COLLINS
Smoke Detectors 10/8/2020 Approved DANIEL COLLINS
Final 10/15/2020 Corrections Issued KATY RAMIREZ
Green Building Final 10/15/2020 Approved KATY RAMIREZ
Final 10/22/2020 Permit Finaled KATY RAMIREZ