4024 N RADFORD AVE 91604

Certificate Information: 4024 N RADFORD AVE 91604

Application / Permit
20016-10000-05633
Plan Check / Job No.
B20LA03759
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
INTERIOR AND EXTERIOR REMODEL WITHIN (E) TWO STORY OFFICE BUILDING WITH STRUCTURAL UPGRADE FOR NEW FLOOR DIAGRAM WITH NEW OPENING AND COLUMN AND STAIRWAY AND FOUNDATION.
Permit Issued
Issued on 5/6/2021
Issuing Office
Current Status
Permit Finaled on 6/15/2022

Permit Application Status History

Submitted 2/25/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 TSE MING HUANG
Corrections Issued 3/23/2020 TSE MING HUANG
Quality Review Completed 3/31/2020 STANLEY RAAP
Building Plans Picked Up 4/7/2020 APPLICANT
Disabled Access Plans Picked Up 4/20/2020 APPLICANT
Green Plans Picked Up 3/9/2021 APPLICANT
Applicant returned to address corrections 3/22/2021 TSE MING HUANG
Applicant returned to address corrections 4/1/2021 TSE MING HUANG
Applicant returned to address corrections 4/19/2021 TSE MING HUANG
Applicant returned to address corrections 4/21/2021 TSE MING HUANG
Plan Check Approved 5/4/2021 TSE MING HUANG
Issued 5/6/2021 APPLICANT
CofO in Progress 12/15/2021 ROBERT DAVIS
No Progress 2/18/2022 ROBERT DAVIS
Permit Finaled 6/15/2022 ROBERT DAVIS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/12/2020 GUILLERMO PETRA
Sewer availability Cleared 5/12/2020 GUILLERMO PETRA
"Q" conditions Cleared 5/13/2020 RUBEN VASQUEZ
ZI Cleared 5/13/2020 RUBEN VASQUEZ
DAS Clearance Cleared 2/4/2021 SOMKIAT SUPANYACHOTSKUL
Green Code Cleared 3/8/2021 KHEDER ALRAZAA

Contact Information

Architect Royalty,, Stuart A; Lic. No.: C25881 15233 VENTURA BLVD STE 1220      SHERMAN OAKS, CA 91403
Contractor West Builders Inc; Lic. No.: 825395-B 120 RAILROAD AVE      POINT RICHMOND, CA 94801
Engineer Ghanim,, Husam; Lic. No.: S5689 1594 CASITAS AVENUE      PASADENA, CA 91103
Engineer Wood,, Kenneth Lee; Lic. No.: C35911 1435 N TEJON      COLORADO SPRINGS, CO 80907

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/28/2021 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/29/2021 Approved ROBERT DAVIS
Reinforced Concrete Frame 6/29/2021 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/30/2021 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/1/2021 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/2/2021 Conditional Approval ROBERT DAVIS
Drywall Nailing 7/26/2021 No Access for Inspection ROBERT DAVIS
Light Gage Steel Frame 7/26/2021 No Access for Inspection ROBERT DAVIS
Drywall Nailing 7/28/2021 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 7/28/2021 Partial Approval ROBERT DAVIS
Drywall Nailing 8/6/2021 Approved DANIEL VARNUM
Interior/Exterior Lathing 8/6/2021 Approved DANIEL VARNUM
Structural Steel Frame 8/10/2021 Partial Inspection ROBERT DAVIS
Deputy Other (see comments) 8/12/2021 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 8/12/2021 Conditional Approval ROBERT DAVIS
T-Bar Ceiling 9/21/2021 Partial Inspection ROBERT DAVIS
T-Bar Ceiling 10/14/2021 Partial Approval ROBERT DAVIS
T-Bar Ceiling 10/19/2021 Conditional Approval ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Not Ready ROBERT DAVIS
Final 12/8/2021 OK to Issue CofO ROBERT DAVIS
Green Building Final 12/8/2021 Approved ROBERT DAVIS
Green Building Rough 12/8/2021 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved ROBERT DAVIS
Smoke Detectors 12/8/2021 Approved ROBERT DAVIS
Wood Frame 12/8/2021 Approved ROBERT DAVIS
Final 6/15/2022 Permit Finaled ROBERT DAVIS