250 S ROSSMORE AVE 90004

Certificate Information: 250 S ROSSMORE AVE 90004

Application / Permit
20016-10000-05608
Plan Check / Job No.
B20LA03744
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Private School
Work Description
(E) PRIVATE SCHOOL REMODEL OF: 1. RENOVATION OF EXISTING BASEMENT LOCKER ROOM, OFFICE, AND CLASSROOMS. 2. RENOVATION OF EXISTING STAGE, AUDITORIUM, AND UPGRADE TO ADA COMPLIANT RESTROOMS. 3. REMOVATION OF EXISTING OUTDOOR PLAZA AND LANDSCAPING.
Permit Issued
Issued on 9/17/2020
Issuing Office
Current Status
Permit Finaled on 11/23/2021

Permit Application Status History

Submitted 2/25/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 HERNAN ARREOLA
Disabled Access Plans Picked Up 3/16/2020 APPLICANT
Corrections Issued 3/31/2020 HERNAN ARREOLA
Quality Review Completed 4/6/2020 BILL STUTSMAN
Building Plans Picked Up 4/7/2020 APPLICANT
Applicant returned to address corrections 4/17/2020 HERNAN ARREOLA
Applicant returned to address corrections 6/12/2020 HERNAN ARREOLA
Green Plans Picked Up 6/12/2020 APPLICANT
Applicant returned to address corrections 6/29/2020 HERNAN ARREOLA
Applicant returned to address corrections 9/3/2020 HERNAN ARREOLA
Plan Check Approved 9/10/2020 HERNAN ARREOLA
Issued 9/17/2020 APPLICANT
Permit Finaled 11/22/2021 TIMOTHY BUXTON

Permit Application Clearance Information

Miscellaneous Cleared 4/24/2020 NOAH MCCOY
ZA Case Cleared 4/24/2020 NOAH MCCOY
ZA Case Cleared 4/24/2020 NOAH MCCOY
ZA Case Cleared 4/24/2020 NOAH MCCOY
HPOZ Cleared 5/5/2020 SUKI GERSHENHORN
Historic monument Cleared 5/5/2020 SUKI GERSHENHORN
ZI Cleared 5/5/2020 SUKI GERSHENHORN
Green Code Cleared 5/28/2020 KHEDER ALRAZAA
Eng Process Fee Ord 176,300 Cleared 5/29/2020 AVALYN KAMACHI
Excavation more than 5-ft deep Cleared 6/5/2020 CALOSHA APPROVED
DAS Clearance Cleared 8/28/2020 SHINE LIN
Fire Marshall Fire Life Safety Cleared 9/11/2020 OSCAR SALGADO JR
Roof/Waste drainage to street Cleared 9/14/2020 JUAN ASHTON

Contact Information

Architect Masotta,, John Joseph; Lic. No.: C24805 391 S BURNSIDE AVE      LOS ANGELES, CA 90036
Contractor Del Amo Construction Inc; Lic. No.: 744458-B 23840 MADISON STREET      TORRANCE, CA 90505
Engineer Reynolds,, Aaron D'Angelo; Lic. No.: S4338 4022 JOELTON DRIVE      AGOURA HILLS, CA 91301

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/23/2020 Approved JONATHAN QUACH
Deputy Grading 10/19/2020 Conditional Approval TIMOTHY BUXTON
Deputy Grading 10/20/2020 Conditional Approval TIMOTHY BUXTON
Deputy Grading 10/21/2020 Conditional Approval TIMOTHY BUXTON
Deputy Grading 10/22/2020 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 10/28/2020 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 10/29/2020 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 10/30/2020 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 11/9/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 11/13/2020 Conditional Approval KATY RAMIREZ
Reinforced Concrete Frame 11/13/2020 Partial Approval TIMOTHY BUXTON
Deputy Steel/Welding 11/20/2020 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 11/20/2020 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 12/2/2020 Partial Approval TIMOTHY BUXTON
Deputy Steel/Welding 12/10/2020 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 12/11/2020 Conditional Approval TIMOTHY BUXTON
Pre-Inspection 12/11/2020 Corrections Issued TIMOTHY BUXTON
Footing/Foundation/Slab 12/28/2020 Partial Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 1/7/2021 Partial Approval TIMOTHY BUXTON
Wood Frame 1/7/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 1/8/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 1/13/2021 Partial Approval TIMOTHY BUXTON
Insulation 1/13/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 1/19/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 1/19/2021 Partial Approval TIMOTHY BUXTON
Deputy Steel/Welding 1/21/2021 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 1/21/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 1/27/2021 Partial Approval TIMOTHY BUXTON
Insulation 1/27/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 2/11/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 2/11/2021 Not Ready for Inspection TIMOTHY BUXTON
Footing/Foundation/Slab 2/19/2021 Partial Approval TIMOTHY BUXTON
Structural Steel Frame 2/19/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 2/26/2021 Partial Approval TIMOTHY BUXTON
Grading Pre-Inspection 3/8/2021 Partial Inspection DANIEL COLLINS
Wood Frame 3/8/2021 Partial Approval DANIEL COLLINS
Grading Pre-Inspection 3/9/2021 Partial Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 3/17/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 3/17/2021 Partial Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Partial Approval TIMOTHY BUXTON
Wood Frame 3/24/2021 Partial Approval TIMOTHY BUXTON
Insulation 3/30/2021 Partial Approval TIMOTHY BUXTON
Special/Order Compliance 3/30/2021 Approved TIMOTHY BUXTON
Deputy Fireproofing 4/5/2021 Conditional Approval TIMOTHY BUXTON
Drywall Nailing 4/5/2021 Partial Approval TIMOTHY BUXTON
Insulation 4/5/2021 Partial Approval TIMOTHY BUXTON
Deputy Fireproofing 4/6/2021 Conditional Approval TIMOTHY BUXTON
Deputy Fireproofing 4/7/2021 Conditional Approval TIMOTHY BUXTON
Drywall Nailing 4/15/2021 Partial Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Partial Approval TIMOTHY BUXTON
Insulation 5/3/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 5/3/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 5/10/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 5/10/2021 Partial Approval TIMOTHY BUXTON
Deputy Fireproofing 5/11/2021 Conditional Approval TIMOTHY BUXTON
Deputy Fireproofing 5/12/2021 Conditional Approval TIMOTHY BUXTON
Deputy Fireproofing 5/13/2021 Conditional Approval TIMOTHY BUXTON
Insulation 5/17/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 5/17/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 6/1/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 6/15/2021 Partial Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 6/15/2021 Partial Approval TIMOTHY BUXTON
Interior/Exterior Lathing 6/15/2021 Partial Approval TIMOTHY BUXTON
Green Building Rough 6/21/2021 Not Ready for Inspection JONATHAN QUACH
Special/Order Compliance 6/21/2021 Not Ready for Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 6/23/2021 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 6/23/2021 Not Ready for Inspection TIMOTHY BUXTON
Reinforced Concrete Frame 6/25/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 7/2/2021 Partial Approval JONATHAN QUACH
Reinforced Concrete Frame 7/2/2021 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 7/9/2021 Partial Approval JONATHAN QUACH
Green Building Rough 7/9/2021 Not Ready for Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 7/20/2021 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 7/21/2021 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 7/23/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 7/28/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 8/2/2021 Partial Approval TIMOTHY BUXTON
Special/Order Compliance 8/11/2021 Approved TIMOTHY BUXTON
T-Bar Ceiling 8/19/2021 Approved TIMOTHY BUXTON
Green Building Final 8/20/2021 Approved TIMOTHY BUXTON
T-Bar Ceiling 8/20/2021 Approved TIMOTHY BUXTON
Special/Order Compliance 9/7/2021 Approved TIMOTHY BUXTON
Final 11/22/2021 Permit Finaled TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Approved TIMOTHY BUXTON
Smoke Detectors 11/22/2021 Approved TIMOTHY BUXTON