5151 N TEESDALE AVE 91607

Certificate Information: 5151 N TEESDALE AVE 91607

Application / Permit
20016-10000-05273
Plan Check / Job No.
B20LA03481
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK PER TYPE V SHEET.
Permit Issued
Issued on 6/29/2020
Issuing Office
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2020 APPLICANT
Assigned to Plan Check Engineer 2/21/2020 FARSHAD ALIMOHAMADI
Corrections Issued 2/26/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 5/12/2020 FARSHAD ALIMOHAMADI
Issued 6/29/2020 APPLICANT
CofO in Progress 12/16/2020 BRENDAN LOONEY
CofO Issued 2/13/2021 MICHAEL SMITH
Permit Finaled 2/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/27/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/27/2020 CELINA MORENO
Sewer availability Cleared 2/27/2020 CELINA MORENO
Construction near power lines Cleared 4/23/2020 RIDWAN HARDY
Specific Plan Cleared 4/27/2020 OLGA AYALA

Contact Information

Contractor S E S Builders Inc; Lic. No.: 1030945-B 15643 SHERMAN WAY #120      VAN NUYS, CA 91406

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/1/2020 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 7/6/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 7/22/2020 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 7/22/2020 Approved BRENDAN LOONEY
PLUMBING-Rough 7/22/2020 Approved BRENDAN LOONEY
Sewer 7/22/2020 Approved BRENDAN LOONEY
Underground Mechanical 7/22/2020 Approved BRENDAN LOONEY
Interior/Exterior Lathing 7/30/2020 Partial Approval BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 7/30/2020 Approved BRENDAN LOONEY
Wood Frame 7/30/2020 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Approved BRENDAN LOONEY
Insulation 8/7/2020 Approved BRENDAN LOONEY
Drywall Nailing 8/14/2020 Approved BRENDAN LOONEY
Interior/Exterior Lathing 8/14/2020 Approved BRENDAN LOONEY
Shower Pan 8/14/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 11/13/2020 Approved BEAU COLLINS
ELECTRICAL-Final 11/13/2020 Approved BEAU COLLINS
Final 11/13/2020 Partial Inspection BEAU COLLINS
Green Building Final 11/13/2020 Approved BEAU COLLINS
Green Building Rough 11/13/2020 Approved BEAU COLLINS
HVAC-Final 11/13/2020 Approved BEAU COLLINS
PLUMBING-Final 11/13/2020 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 11/13/2020 SGSOV Approved BEAU COLLINS
Smoke Detectors 11/13/2020 Approved BEAU COLLINS
Special/Order Compliance 11/17/2020 Corrections Issued BEAU COLLINS
Final 11/19/2020 Corrections Issued BRENDAN LOONEY
Final 12/1/2020 Corrections Issued BRENDAN LOONEY
Final 12/15/2020 OK to Issue CofO BRENDAN LOONEY