3007 N TYBURN ST 90039
Certificate Information: 3007 N TYBURN ST 90039
- Application / Permit
- 20016-10000-05113
- Plan Check / Job No.
- B20LA03354
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing accesory building to detached ADU per state law GCS 65852.2(e)(1)(A). All works per Wood Frame Prescriptive Provisions.
- Permit Issued
- Issued on 6/24/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2020 | HELEN NGUYEN |
| Corrections Issued | 2/27/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/9/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/18/2020 | HELEN NGUYEN |
| Plan Check Approved | 6/1/2020 | HELEN NGUYEN |
| Issued | 6/24/2020 | LADBS |
| Building Plans Picked Up | 6/29/2020 | APPLICANT |
| CofO in Progress | 2/11/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 2/13/2021 | DEROLD HAUFF |
| CofO Issued | 2/13/2021 | DEROLD HAUFF |
| Permit Finaled | 2/13/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 4/28/2020 | EMIL KYUPELYAN |
| ZI | Cleared | 5/8/2020 | RUBEN VASQUEZ |
| Hydrant and Access approval | Cleared | 5/15/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Kafe Design & Construction; Lic. No.: 977712-B | 317 E RAMONA ROAD ALHAMBRA, CA 91801 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/2/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/2/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/2/2020 | Approved | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 7/6/2020 | No Access for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2020 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/29/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2020 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/29/2020 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 7/29/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 8/3/2020 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 8/5/2020 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 9/11/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 9/11/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 9/11/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 9/11/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/11/2020 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/11/2020 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/11/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 2/1/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 2/1/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 2/1/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 2/1/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 2/11/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 2/11/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |
| HVAC-Final | 2/11/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 2/11/2021 | Approved | HAMIK HARTOUNIAN |