1515 E 15TH ST 90021

Certificate Information: 1515 E 15TH ST 90021

Application / Permit
20016-10000-05059
Plan Check / Job No.
B20LA03328
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
INSTALLATION OF ELEVATOR SHAFT AND ELEVATOR MACHINE ROOM WITHIN EXISTING COMMERICAL BUILDING.
Permit Issued
Issued on 8/6/2020
Issuing Office
Metro
Current Status
Permit Finaled on 3/24/2021

Permit Application Status History

Submitted 2/20/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 ARMEN JIVALAGIAN
Corrections Issued 3/27/2020 ARMEN JIVALAGIAN
Disabled Access Plans Picked Up 3/31/2020 APPLICANT
Quality Review Completed 4/2/2020 TIEN JEN WANG
Building Plans Picked Up 4/8/2020 APPLICANT
Green Plans Picked Up 7/15/2020 APPLICANT
Plan Check Approved 7/24/2020 ARMEN JIVALAGIAN
Issued 8/6/2020 APPLICANT
Permit Finaled 3/24/2021 DANIEL COLLINS

Permit Application Clearance Information

Green Code Cleared 5/6/2020 KHEDER ALRAZAA
DAS Clearance Cleared 6/26/2020 EDDIE GARIN
"D" conditions Cleared 7/15/2020 MIGUEL GAMBOA

Contact Information

Architect Malak,, Hany; Lic. No.: C27490 360 PINE TREE LANE      MONROVIA, CA 91016
Contractor Parker Brown Inc; Lic. No.: 689613-B 6727 VARIEL AVENUE      CANOGA PARK, CA 913032811
Engineer Faghihi,, Mahmoud; Lic. No.: S5789 888 S FIGUEROA STREET 18TH FLOOR      LOS ANGELES, CA 90017

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 8/7/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 8/10/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 8/19/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 8/19/2020 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 9/2/2020 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 9/3/2020 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 9/8/2020 Conditional Approval DANIEL COLLINS
Drywall Nailing 9/9/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 9/9/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 9/15/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 9/24/2020 Approved LANNY MERRICK
Light Gage Steel Frame 9/24/2020 Approved LANNY MERRICK
Deputy Steel/Welding 12/16/2020 Conditional Approval DANIEL COLLINS
Final 3/24/2021 Permit Finaled DANIEL COLLINS
Green Building Final 3/24/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Approved DANIEL COLLINS
Smoke Detectors 3/24/2021 Approved DANIEL COLLINS