5647 N CARTWRIGHT AVE 91601
Certificate Information: 5647 N CARTWRIGHT AVE 91601
- Application / Permit
- 20016-10000-04971
- Plan Check / Job No.
- B20LA03224
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LA BC CH. 93. INSTALL (2) SPECIAL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 11/24/2020
- Issuing Office
- Current Status
- CofC Issued on 5/14/2024
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | JESSE VIDUYA |
| Corrections Issued | 2/24/2020 | JESSE VIDUYA |
| Quality Review Completed | 2/26/2020 | SAI KHUM |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Applicant returned to address corrections | 3/17/2020 | JESSE VIDUYA |
| Plan Check Approved | 4/2/2020 | JESSE VIDUYA |
| Issued | 11/24/2020 | APPLICANT |
| OK for CofC | 2/15/2024 | KENNETH ROBERTS |
| CofC Issued | 5/14/2024 | KENNETH ROBERTS |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/18/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 3/27/2020 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 10/26/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | After Before Creations Inc; Lic. No.: 876769-B | 2411 WEST EMPIRE AVE BURBANK, CA 91505 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 6631 MURIETTA AVE LOS ANGELES, CA 91405 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/5/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 6/15/2021 | Corrections Issued | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 6/16/2021 | No Access for Inspection | JOE VELASQUEZ |
| Insulation | 7/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Insulation | 7/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Insulation | 7/16/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 7/16/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 7/30/2021 | Approved | KENNETH ROBERTS |
| Final | 2/13/2024 | Partial Approval | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 2/13/2024 | Approved | KENNETH ROBERTS |
| Final | 2/15/2024 | OK for CofC | KENNETH ROBERTS |