757 S ALAMEDA ST 90021
Certificate Information: 757 S ALAMEDA ST 90021
- Application / Permit
- 20016-10000-04852
- Plan Check / Job No.
- B20LA03127
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- 2ND FLOOR TI WITHIN 6-STORY BUILDING TO INCLUDE OFFICE SUITES AND COMMON AREAS, NEW PARTITIONS, INTERIOR GLASS. NO EXTERIOR WORK.
- Permit Issued
- Issued on 6/2/2020
- Issuing Office
- Current Status
- Permit Finaled on 11/16/2020
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | ALBERT SERVIN |
| Corrections Issued | 3/10/2020 | ALBERT SERVIN |
| Quality Review Completed | 3/12/2020 | KEN GILL |
| Disabled Access Plans Picked Up | 3/17/2020 | APPLICANT |
| Green Plans Picked Up | 5/12/2020 | APPLICANT |
| Plan Check Approved | 5/20/2020 | ALBERT SERVIN |
| Issued | 6/2/2020 | APPLICANT |
| Permit Finaled | 11/16/2020 | KATY RAMIREZ |
Permit Application Clearance Information
| Green Code | Cleared | 4/16/2020 | ALBERT SERVIN |
| Redevelopment Project Area | Cleared | 4/20/2020 | DAVID URITA |
| DAS Clearance | Cleared | 5/7/2020 | ALBERT SERVIN |
Contact Information
| Contractor | J R M Construction Management West Llc; Lic. No.: 1013928-B | 959 SOUTH COAST DR #495 COSTA MESA, CA 92626 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/6/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Other (see comments) | 7/16/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 7/21/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 7/31/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Other (see comments) | 8/11/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 8/12/2020 | Conditional Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 8/24/2020 | Corrections Issued | KATY RAMIREZ |
| Drywall Nailing | 9/8/2020 | Partial Approval | KATY RAMIREZ |
| Insulation | 9/8/2020 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 9/8/2020 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 9/23/2020 | Partial Approval | KATY RAMIREZ |
| Insulation | 9/23/2020 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 9/23/2020 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 10/23/2020 | Approved | KATY RAMIREZ |
| Final | 11/12/2020 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 11/12/2020 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 11/12/2020 | Approved | KATY RAMIREZ |
| Final | 11/16/2020 | Permit Finaled | KATY RAMIREZ |
| Green Building Final | 11/16/2020 | Approved | KATY RAMIREZ |