4569 E CATALPA ST 90032

Certificate Information: 4569 E CATALPA ST 90032

Application / Permit
20016-10000-04832
Plan Check / Job No.
B20LA03113
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 2-CAR GARAGE INTO AN ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 5/11/2020
Issuing Office
Current Status
CofO Issued on 11/13/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 2/25/2020 MONICA RAMIREZ
Corrections Issued 2/25/2020 MONICA RAMIREZ
Plan Check Approved 4/23/2020 SHANGQIN XIE
Issued 5/11/2020 APPLICANT
Building Plans Picked Up 5/15/2020 APPLICANT
CofO in Progress 11/10/2020 ELMER BLAND
Permit Finaled 11/13/2020 DEROLD HAUFF
CofO Issued 11/13/2020 DEROLD HAUFF
Permit Finaled 11/13/2020 DEROLD HAUFF

Permit Application Clearance Information

"D" conditions Cleared 4/6/2020 RICHARD REASER
"Q" conditions Cleared 4/6/2020 RICHARD REASER
Address approval Cleared 4/14/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 4/14/2020 RENZ SORIANO
Sewer availability Cleared 4/14/2020 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/18/2020 Not Ready for Inspection OSVALDO PARAMO
Sewer 5/18/2020 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 5/18/2020 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 5/21/2020 Approved ENRIQUE MIRELES
Sewer 5/21/2020 Approved ENRIQUE MIRELES
Underground Mechanical 5/21/2020 Approved ENRIQUE MIRELES
Gas Test 7/1/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 7/1/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/2/2020 Approved RUBEN SALAS
HVAC-Rough 7/2/2020 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 7/2/2020 Approved RUBEN SALAS
BUILDING-Rough-Frame 7/13/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Approved ENRIQUE MIRELES
Green Building Rough 7/13/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/13/2020 Not Ready for Inspection ENRIQUE MIRELES
Insulation 7/27/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/31/2020 Approved ENRIQUE MIRELES
Drywall Nailing 8/7/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 8/20/2020 Approved CHRISTOPHER DELLEFIELD
Final 9/28/2020 Corrections Issued OSVALDO PARAMO
Gas Test 9/28/2020 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 9/28/2020 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/28/2020 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 9/28/2020 Not Ready for Inspection OSVALDO PARAMO
Final 10/14/2020 Corrections Issued COREY HUPP
Gas Test 10/14/2020 Not Ready for Inspection COREY HUPP
Green Building Final 10/14/2020 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 10/14/2020 SGSOV Not Ready COREY HUPP
Smoke Detectors 10/14/2020 Approved COREY HUPP
ELECTRICAL-Final 10/23/2020 Corrections Issued SCOTT FINNILA
Final 10/23/2020 Corrections Issued SCOTT FINNILA
Gas Test 10/23/2020 Approved SCOTT FINNILA
Green Building Final 10/23/2020 Approved SCOTT FINNILA
HVAC-Final 10/23/2020 Approved SCOTT FINNILA
PLUMBING-Final 10/23/2020 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Approved SCOTT FINNILA
Service/Power Release 10/23/2020 Partial Inspection SCOTT FINNILA
Final 10/28/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 11/9/2020 Approved SCOTT FINNILA
Final 11/9/2020 Partial Approval SCOTT FINNILA
PLUMBING-Final 11/9/2020 Approved SCOTT FINNILA
Final 11/10/2020 OK to Issue CofO ELMER BLAND