- Fire damaged repair to existing single family dwelling including remove and replace ceiling joists, roof rafters, patching drywalls. Remove and replace all windows
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Metro
- Current Status
- Issued on 3/6/2020
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2020 | VU NGUYEN |
| Corrections Issued | 2/18/2020 | VU NGUYEN |
| Plan Check Approved | 3/6/2020 | JOHNNY WU |
| Issued | 3/6/2020 | LADBS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Paglia & Associates Construction Inc; Lic. No.: 485114-B | 2790 EAST REGAL PARK DR ANAHEIM, CA 92806 |
| Engineer | Ionescu,, Benjamin; Lic. No.: C65482 | 55 GARDENHOUSE WAY IRVINE, CA 92620 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/28/2020 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 8/5/2020 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/4/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/4/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/4/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/4/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/8/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/8/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/8/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 1/8/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/8/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/2/2021 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 2/2/2021 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 2/2/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 6/2/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/2/2021 | Approved | HAMIK HARTOUNIAN |