20065 W RINALDI ST 160 91326
Certificate Information: 20065 W RINALDI ST 160 91326
- Application / Permit
- 20016-10000-04720
- Plan Check / Job No.
- B20LA03029
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- INTERIOR TENANT IMPROVEMENT TO (E) RESTAURANT. NEW KITCHEN, DINING AREA, AND TWO SINGLE-USER TOILET ROOM.
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/30/2022
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | KEVIN MORALES |
| Corrections Issued | 3/10/2020 | KEVIN MORALES |
| Quality Review Completed | 3/14/2020 | YOUNG KIM |
| Disabled Access Plans Picked Up | 3/17/2020 | APPLICANT |
| Plan Check Approved | 3/10/2021 | KEVIN MORALES |
| Building Plans Picked Up | 3/11/2021 | APPLICANT |
| Issued | 4/20/2021 | APPLICANT |
| Permit Finaled | 3/29/2022 | JEFFREY FULTON |
Permit Application Clearance Information
| Food Service Establishment | Cleared | 1/12/2021 | JASH PATEL |
| DAS Clearance | Cleared | 2/9/2021 | KEVIN MORALES |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/22/2021 | GABRIEL ROBLES |
| Food establishment approval | Cleared | 3/3/2021 | LACDHS APPROVED |
| Specific Plan | Cleared | 3/9/2021 | DANG NGUYEN |
Contact Information
| Architect | Yoo,, Won Warren; Lic. No.: C37091 | 2540 EVELYN STREET MONTROSE, CA 91020 |
| Contractor | Solid Construction Company Inc; Lic. No.: 836983-B | 883 CRENSHAW BLVD LOS ANGELES, CA 90005 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/7/2021 | Conditional Approval | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 5/10/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 6/8/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 7/30/2021 | Approved | DANIEL VARNUM |
| Drywall Nailing | 9/8/2021 | Partial Approval | PAUL DAVIDSON |
| T-Bar Ceiling | 11/15/2021 | Approved | JONATHAN QUACH |
| Deputy Steel/Welding | 1/5/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Fireproofing | 1/27/2022 | Conditional Approval | JEFFREY FULTON |
| Final | 3/25/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 3/25/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 3/25/2022 | Approved | JEFFREY FULTON |
| Final | 3/29/2022 | Permit Finaled | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 3/29/2022 | Approved | JEFFREY FULTON |