20065 W RINALDI ST 160 91326

Certificate Information: 20065 W RINALDI ST 160 91326

Application / Permit
20016-10000-04720
Plan Check / Job No.
B20LA03029
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
INTERIOR TENANT IMPROVEMENT TO (E) RESTAURANT. NEW KITCHEN, DINING AREA, AND TWO SINGLE-USER TOILET ROOM.
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
Permit Finaled on 3/30/2022

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 KEVIN MORALES
Corrections Issued 3/10/2020 KEVIN MORALES
Quality Review Completed 3/14/2020 YOUNG KIM
Disabled Access Plans Picked Up 3/17/2020 APPLICANT
Plan Check Approved 3/10/2021 KEVIN MORALES
Building Plans Picked Up 3/11/2021 APPLICANT
Issued 4/20/2021 APPLICANT
Permit Finaled 3/29/2022 JEFFREY FULTON

Permit Application Clearance Information

Food Service Establishment Cleared 1/12/2021 JASH PATEL
DAS Clearance Cleared 2/9/2021 KEVIN MORALES
Eng Process Fee Ord 176,300 Cleared 2/22/2021 GABRIEL ROBLES
Sewer availability Cleared 2/22/2021 GABRIEL ROBLES
Food establishment approval Cleared 3/3/2021 LACDHS APPROVED
Specific Plan Cleared 3/9/2021 DANG NGUYEN

Contact Information

Architect Yoo,, Won Warren; Lic. No.: C37091 2540 EVELYN STREET      MONTROSE, CA 91020
Contractor Solid Construction Company Inc; Lic. No.: 836983-B 883 CRENSHAW BLVD      LOS ANGELES, CA 90005

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/7/2021 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/10/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/8/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/30/2021 Approved DANIEL VARNUM
Drywall Nailing 9/8/2021 Partial Approval PAUL DAVIDSON
T-Bar Ceiling 11/15/2021 Approved JONATHAN QUACH
Deputy Steel/Welding 1/5/2022 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 1/27/2022 Conditional Approval JEFFREY FULTON
Final 3/25/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 3/25/2022 Approved JEFFREY FULTON
Final 3/29/2022 Permit Finaled JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV Approved JEFFREY FULTON
Smoke Detectors 3/29/2022 Approved JEFFREY FULTON