4527 N GRIFFIN AVE 90031

Certificate Information: 4527 N GRIFFIN AVE 90031

Application / Permit
20016-10000-04707
Plan Check / Job No.
B20LA03019
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REPLACEMENT OF EXISTING BRICK FIREPLACE AND CHIMNEY WITH CMU AND METAL STUDS
Permit Issued
Issued on 5/14/2020
Issuing Office
Metro
Current Status
Issued on 5/14/2020

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 2/18/2020 ADAM HEGAZI
Corrections Issued 2/18/2020 ADAM HEGAZI
Plan Check Approved 2/18/2020 ADAM HEGAZI
Issued 5/14/2020 LADBS
Building Plans Picked Up 4/30/2021 APPLICANT

Permit Application Clearance Information

"D" conditions Cleared 2/18/2020 SARAHI ORTEGA
"Q" conditions Cleared 2/18/2020 SARAHI ORTEGA
HPOZ Cleared 2/18/2020 KATIE DEBIASE
Historic monument Cleared 2/18/2020 KATIE DEBIASE

Contact Information

Architect Asamoah,, B Kwesi; Lic. No.: C36558 850 ROSE AVENUE      VENICE, CA 90291
Architect Day,, Christopher Francis; Lic. No.: C36682 522 N. NORMANDIE AVE   APT #3    LOS ANGELES, CA 90004
Contractor Oakwood Construction; Lic. No.: 762828-B 4955 E HUNTER AVE      ANAHEIM, CA 92807

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Masonry Wall/Backfill 9/1/2020 Approved ENRIQUE MIRELES
Reinforced Concrete Frame 9/1/2020 Approved ENRIQUE MIRELES
Reinforced Masonry Frame 9/1/2020 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 9/15/2020 No Access for Inspection ELMER BLAND
Deputy Reinf. Masonry 9/23/2020 No Access for Inspection ELMER BLAND
Reinforced Masonry Frame 10/1/2020 Corrections Issued COREY HUPP
Reinforced Masonry Frame 10/13/2020 Partial Approval COREY HUPP
Reinforced Masonry Frame 10/21/2020 OK to Expire Permit COREY HUPP
Reinforced Masonry Frame 10/30/2020 Partial Approval COREY HUPP
Interior/Exterior Lathing 12/3/2020 Not Ready for Inspection COREY HUPP
Light Gage Steel Frame 12/3/2020 Corrections Issued COREY HUPP
Structural Steel Frame 12/9/2020 Not Ready for Inspection COREY HUPP
Structural Steel Frame 12/17/2020 Corrections Issued COREY HUPP
Light Gage Steel Frame 1/5/2021 Corrections Issued OSVALDO PARAMO
Wood Frame 1/5/2021 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 1/22/2021 Approved COREY HUPP