409 S EDINBURGH AVE 90048

Certificate Information: 409 S EDINBURGH AVE 90048

Application / Permit
20016-10000-04618
Plan Check / Job No.
B20LA02986
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) storage on first floor and recreation room on 2nd floor into an Accessory Dwelling Unit per detached ADU per ordinance.
Permit Issued
Issued on 3/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 FARSHAD ALIMOHAMADI
Corrections Issued 2/20/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 3/11/2020 HELEN NGUYEN
Issued 3/13/2020 LADBS
CofO in Progress 4/19/2023 JEREMY TODD
Permit Finaled 5/2/2023 DANIEL ORRANTE
CofO Issued 5/2/2023 DANIEL ORRANTE
Permit Finaled 5/2/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/11/2020 CELINA MORENO
Construction near power lines Cleared 3/11/2020 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 3/11/2020 CELINA MORENO
Sewer availability Cleared 3/11/2020 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 4/2/2020 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 4/2/2020 Approved EVAN COOPER
Insulation 4/2/2020 Approved EVAN COOPER
PLUMBING-Rough 4/2/2020 Approved EVAN COOPER
Shower Pan 4/2/2020 Approved EVAN COOPER
Special/Order Compliance 4/2/2020 Approved EVAN COOPER
ELECTRICAL-Rough 4/3/2020 Approved EVAN COOPER
Shower Pan 4/3/2020 Approved EVAN COOPER
Drywall Nailing 4/9/2020 Partial Approval EVAN COOPER
Interior/Exterior Lathing 4/9/2020 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 7/10/2020 Not Ready for Inspection KENNETH NAGLE
Final 7/10/2020 Not Ready for Inspection KENNETH NAGLE
METHANE-Final 7/10/2020 Not Ready for Inspection KENNETH NAGLE
METHANE-Rough 7/10/2020 Approved KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 7/10/2020 SGSOV Approved KENNETH NAGLE
Smoke Detectors 7/10/2020 Corrections Issued KENNETH NAGLE
BUILDING-Rough-Frame 7/20/2020 Approved KENNETH NAGLE
Final 7/20/2020 Partial Inspection KENNETH NAGLE
METHANE-Final 7/20/2020 Approved KENNETH NAGLE
METHANE-Rough 7/20/2020 Approved KENNETH NAGLE
Smoke Detectors 7/20/2020 Approved KENNETH NAGLE
ELECTRICAL-Final 3/28/2023 Corrections Issued JEREMY TODD
Final 3/28/2023 Corrections Issued JEREMY TODD
HVAC-Final 3/28/2023 Not Ready for Inspection JEREMY TODD
PLUMBING-Final 3/28/2023 Approved JEREMY TODD
ELECTRICAL-Final 4/18/2023 Approved JEREMY TODD
Final 4/18/2023 OK to Issue CofO JEREMY TODD
HVAC-Final 4/18/2023 Approved JEREMY TODD
PLUMBING-Final 4/18/2023 Approved JEREMY TODD