1732 N EL CERRITO PL 90028

Certificate Information: 1732 N EL CERRITO PL 90028

Application / Permit
20016-10000-04528
Plan Check / Job No.
B20LA02937
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: Seismic Reinforcement at building parking garage using (3) steel special cantilevered columns with grade beams.
Permit Issued
Issued on 6/30/2020
Issuing Office
Current Status
CofC Issued on 11/10/2020

Permit Application Status History

Submitted 2/14/2020 APPLICANT
Assigned to Plan Check Engineer 3/4/2020 DANIEL SANJUAN
Corrections Issued 3/18/2020 DANIEL SANJUAN
Quality Review Completed 3/26/2020 HANS SANTIAGO
Plan Check Approved 5/27/2020 DANIEL SANJUAN
Issued 6/30/2020 APPLICANT
OK for CofC 11/6/2020 SABAS ALONSO
CofC Issued 11/10/2020 DAVID TSAU

Permit Application Clearance Information

Historic Resource Verification Cleared 5/12/2020 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 5/12/2020 DAVID URITA
Tenant Habitability Plan Cleared 6/24/2020 STEVEN HOFSTAD

Contact Information

Contractor Repipe 1 Restoration Inc; Lic. No.: 1003868-B       ,
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/20/2020 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 9/17/2020 Approved MARK FERRARI
Structural Steel Frame 9/17/2020 Approved MARK FERRARI
Wood Frame 9/17/2020 Approved MARK FERRARI
Interior/Exterior Lathing 9/30/2020 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 10/13/2020 SGSOV Not Ready JONATHAN QUACH
Final 10/28/2020 Conditional Approval JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 10/28/2020 SGSOV Approved JONATHAN QUACH
Smoke Detectors 10/28/2020 Approved JONATHAN QUACH
Final 11/6/2020 OK for CofC SABAS ALONSO