4014 1/2 W 29TH ST 90018
Certificate Information: 4014 1/2 W 29TH ST 90018
- Application / Permit
- 20016-10000-04520
- Plan Check / Job No.
- B20LA02933
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) garage and attached storage into an Accessory Dwelling Unit. All works per Wood Frame Prescriptive Provisions.
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 9/27/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | ADAM HEGAZI |
| Corrections Issued | 2/14/2020 | ADAM HEGAZI |
| Plan Check Approved | 2/14/2020 | HELEN NGUYEN |
| Issued | 3/3/2020 | LADBS |
| CofO in Progress | 9/1/2020 | STUART CHAPMAN |
| CofO in Progress | 9/16/2020 | STUART CHAPMAN |
| Permit Finaled | 9/27/2020 | DEROLD HAUFF |
| CofO Issued | 9/27/2020 | DEROLD HAUFF |
| Permit Finaled | 9/27/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2020 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/14/2020 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/31/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/31/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/31/2020 | Partial Approval | ENRIQUE MIRELES |
| Wood Frame | 3/31/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/22/2020 | Approved | STUART CHAPMAN |
| Insulation | 4/22/2020 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/22/2020 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 4/22/2020 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/28/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/28/2020 | Approved | STUART CHAPMAN |
| Drywall Nailing | 5/11/2020 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/11/2020 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/17/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 7/17/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 7/17/2020 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 7/17/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/17/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 7/17/2020 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 7/17/2020 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 7/17/2020 | Approved | STUART CHAPMAN |
| Final | 7/23/2020 | Partial Approval | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 7/23/2020 | SGSOV Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/31/2020 | Approved | STUART CHAPMAN |
| Final | 8/31/2020 | Conditional Approval | STUART CHAPMAN |
| Green Building Final | 8/31/2020 | Approved | STUART CHAPMAN |
| HVAC-Final | 8/31/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/31/2020 | Approved | STUART CHAPMAN |
| Final | 9/15/2020 | OK to Issue CofO | STUART CHAPMAN |
| Service/Power Release | 9/15/2020 | Approved | STUART CHAPMAN |