4014 1/2 W 29TH ST 90018

Certificate Information: 4014 1/2 W 29TH ST 90018

Application / Permit
20016-10000-04520
Plan Check / Job No.
B20LA02933
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) garage and attached storage into an Accessory Dwelling Unit. All works per Wood Frame Prescriptive Provisions.
Permit Issued
Issued on 3/3/2020
Issuing Office
San Pedro
Current Status
CofO Issued on 9/27/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2020 APPLICANT
Assigned to Plan Check Engineer 2/14/2020 ADAM HEGAZI
Corrections Issued 2/14/2020 ADAM HEGAZI
Plan Check Approved 2/14/2020 HELEN NGUYEN
Issued 3/3/2020 LADBS
CofO in Progress 9/1/2020 STUART CHAPMAN
CofO in Progress 9/16/2020 STUART CHAPMAN
Permit Finaled 9/27/2020 DEROLD HAUFF
CofO Issued 9/27/2020 DEROLD HAUFF
Permit Finaled 9/27/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/14/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/14/2020 JEANETTE VONG
Sewer availability Cleared 2/14/2020 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/31/2020 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 3/31/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 3/31/2020 Partial Approval ENRIQUE MIRELES
Wood Frame 3/31/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 4/22/2020 Approved STUART CHAPMAN
Insulation 4/22/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 4/22/2020 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 4/22/2020 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 4/28/2020 Approved STUART CHAPMAN
PLUMBING-Rough 4/28/2020 Approved STUART CHAPMAN
Drywall Nailing 5/11/2020 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 5/11/2020 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/17/2020 Approved STUART CHAPMAN
ELECTRICAL-Final 7/17/2020 Not Ready for Inspection STUART CHAPMAN
Final 7/17/2020 Corrections Issued STUART CHAPMAN
Green Building Final 7/17/2020 Approved STUART CHAPMAN
Green Building Rough 7/17/2020 Approved STUART CHAPMAN
PLUMBING-Final 7/17/2020 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/17/2020 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 7/17/2020 Approved STUART CHAPMAN
Final 7/23/2020 Partial Approval STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/23/2020 SGSOV Approved STUART CHAPMAN
ELECTRICAL-Final 8/31/2020 Approved STUART CHAPMAN
Final 8/31/2020 Conditional Approval STUART CHAPMAN
Green Building Final 8/31/2020 Approved STUART CHAPMAN
HVAC-Final 8/31/2020 Approved STUART CHAPMAN
PLUMBING-Final 8/31/2020 Approved STUART CHAPMAN
Final 9/15/2020 OK to Issue CofO STUART CHAPMAN
Service/Power Release 9/15/2020 Approved STUART CHAPMAN