4632 E DRUID ST 90032
Certificate Information: 4632 E DRUID ST 90032
- Application / Permit
- 20016-10000-04094
- Plan Check / Job No.
- B20LA02676
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) ATTACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT. WORK PER ENGINEER
- Permit Issued
- Issued on 9/16/2020
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2020 | ADAM HEGAZI |
| Corrections Issued | 2/11/2020 | ADAM HEGAZI |
| Plan Check Approved | 2/27/2020 | GEORGE ALVAREZ |
| Issued | 9/16/2020 | APPLICANT |
| Building Plans Picked Up | 9/17/2020 | APPLICANT |
| CofO in Progress | 9/15/2021 | COREY HUPP |
| CofO in Progress | 10/5/2021 | COREY HUPP |
| No Progress | 2/13/2023 | MICHAEL PELHAM |
| CofO in Progress | 2/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/14/2023 | DANIEL ORRANTE |
| CofO Issued | 2/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| "D" conditions | Cleared | 2/19/2020 | JOSE ROMERO-NAVARRO |
| "Q" conditions | Cleared | 2/19/2020 | JOSE ROMERO-NAVARRO |
| Address approval | Cleared | 2/19/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | JEANIE LAM |
| Sewer availability | Cleared | 2/19/2020 | JEANIE LAM |
| ZI | Cleared | 2/19/2020 | JOSE ROMERO-NAVARRO |
Contact Information
| Contractor | Levet Inc; Lic. No.: 1027447-B | 1110 SONORA AVE #101 GLENDALE, CA 91201 |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/21/2020 | Corrections Issued | COREY HUPP |
| Sewer | 9/21/2020 | Approved | COREY HUPP |
| Footing/Foundation/Slab | 1/11/2021 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 3/23/2021 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/27/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 5/27/2021 | Corrections Issued | OSVALDO PARAMO |
| Wood Frame | 5/27/2021 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 6/4/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 6/17/2021 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/17/2021 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 6/25/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/25/2021 | Partial Approval | WILLIAM WREN |
| Final | 8/19/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 8/19/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/19/2021 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 8/19/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 9/3/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 9/3/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 9/3/2021 | Approved | OSVALDO PARAMO |
| Final | 9/14/2021 | OK to Issue CofO | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 9/14/2021 | SGSOV Approved | COREY HUPP |