1501 W FRANCISCO ST 90501
Certificate Information: 1501 W FRANCISCO ST 90501
- Application / Permit
- 20016-10000-04038
- Plan Check / Job No.
- B20LA02645
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- DATA CENTER TI-AREA OF WORK 77,390 SF. SELECT DEMOLITION AND CONSTRUCTION OF NEW WALLS, DOORS, CEILINGS, WINDOWS, MILLWORK, PARTITION WALLS AND FINISHES ( NO CHANGE OF USE )
- Permit Issued
- Issued on 6/15/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 10/6/2021
Permit Application Status History
| Submitted | 2/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2020 | RACHEL BEYENE |
| Corrections Issued | 2/21/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 4/23/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 5/21/2020 | AUNG SOE |
| Plan Check Approved | 6/9/2020 | ADAM HEGAZI |
| Issued | 6/15/2020 | LADBS |
| Building Plans Picked Up | 6/16/2020 | APPLICANT |
| Permit Finaled | 10/6/2021 | JOEY BUCHANAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Downey,, Michael Rane; Lic. No.: C19329 | 5705 SKYVIEW PLACE RICHMOND, CA 94803 |
| Contractor | J T M Construction Group Inc; Lic. No.: 956584-B | 44 WEST 28TH STREET 11TH FLOOR NEW YORK, NY 10001 |
| Engineer | Lindorfer,, Kurt Randall; Lic. No.: S3157 | 639 FRONT STREET 4TH FL SAN FRANCISCO, CA 94111 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/1/2020 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 7/16/2020 | Approved | JOEY BUCHANAN |
| Light Gage Steel Frame | 7/16/2020 | Partial Approval | JOEY BUCHANAN |
| Light Gage Steel Frame | 8/13/2020 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 8/21/2020 | Approved | JOEY BUCHANAN |
| Light Gage Steel Frame | 8/21/2020 | Partial Approval | JOEY BUCHANAN |
| Structural Steel Frame | 8/21/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 9/11/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 9/15/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 9/18/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 9/22/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 9/24/2020 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 10/2/2020 | Approved | JOEY BUCHANAN |
| Final | 10/8/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Green Building Final | 10/8/2020 | Approved | JOEY BUCHANAN |
| Green Building Rough | 10/8/2020 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2020 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 10/8/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 10/13/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 10/14/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 10/15/2020 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 1/6/2021 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 1/29/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| T-Bar Ceiling | 2/9/2021 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 3/2/2021 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 4/1/2021 | Approved | JOEY BUCHANAN |
| Final | 9/29/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 10/6/2021 | Permit Finaled | JOEY BUCHANAN |