1769 S OGDEN DR 90019

Certificate Information: 1769 S OGDEN DR 90019

Application / Permit
20016-10000-03939
Plan Check / Job No.
B20LA02583
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) SFD, TO COMBINE (E) BEDROOM AND (E) MASTER BEDROOM INTO ONE (N) MASTER BEDROOM WITH WALK IN CLOSET AND MASTER BATHROOM. AND INTERIOR REMODEL OF KITCHEN
Permit Issued
Issued on 11/16/2020
Issuing Office
Current Status
Permit Finaled on 3/11/2021

Permit Application Status History

Submitted 2/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 AMIR DANAI
Corrections Issued 3/26/2020 AMIR DANAI
Quality Review Completed 4/2/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 4/14/2020 APPLICANT
Green Plans Picked Up 5/28/2020 APPLICANT
Plan Check Approved 6/10/2020 AMIR DANAI
Issued 11/16/2020 APPLICANT
Permit Finaled 3/11/2021 JOSEPH MCGARRY

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/18/2020 JUAN ASHTON
Sewer availability Cleared 5/18/2020 JUAN ASHTON
Green Code Cleared 5/28/2020 KHEDER ALRAZAA

Contact Information

Architect Bullock,, Rachel Lane; Lic. No.: C35963 741 N OCCIDENTAL BLVD      LOS ANGELES, CA 90026
Contractor Perkins Michael Construction; Lic. No.: 745473-B 520 S SUNSET CANYON DRIVE      BURBANK, CA 91501
Engineer Sayah,, Daniel Hoshyar; Lic. No.: S6000 15233 VENTURA BLVD 1130      SHERMAN OAKS, CA 91403

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/25/2020 Partial Approval DAVID CHAN
ELECTRICAL-Rough 11/25/2020 Approved DAVID CHAN
Excavation/Setback/Form/Re-Bar 11/25/2020 Approved DAVID CHAN
Footing/Foundation/Slab 11/25/2020 Approved DAVID CHAN
HVAC-Rough 11/25/2020 Corrections Issued DAVID CHAN
PLUMBING-Rough 11/25/2020 Approved DAVID CHAN
Wood Frame 11/25/2020 Partial Approval DAVID CHAN
Drywall Nailing 12/10/2020 Partial Approval DAVID CHAN
Insulation 12/10/2020 Partial Approval DAVID CHAN
Excavation/Setback/Form/Re-Bar 12/15/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 12/15/2020 Partial Approval DAVID CHAN
Insulation 12/15/2020 Partial Approval DAVID CHAN
Shower Pan 12/15/2020 Approved DAVID CHAN
Deputy Reinf. Concrete 12/17/2020 No Access for Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 1/7/2021 Partial Approval DAVID CHAN
Insulation 1/13/2021 Approved DAVID CHAN
Interior/Exterior Lathing 1/13/2021 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 1/15/2021 Approved DAVID CHAN
Interior/Exterior Lathing 1/15/2021 Approved DAVID CHAN
Deputy Wood Construction 1/20/2021 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 1/21/2021 Approved JOSEPH MCGARRY
Drywall Nailing 1/21/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Approved JOSEPH MCGARRY
HVAC-Rough 1/21/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 1/21/2021 Approved JOSEPH MCGARRY
Wood Frame 1/21/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Final 3/5/2021 Approved ROBERT VORHIS
Final 3/5/2021 Corrections Issued ROBERT VORHIS
HVAC-Final 3/5/2021 Approved ROBERT VORHIS
PLUMBING-Final 3/5/2021 Approved ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 3/5/2021 SGSOV Approved ROBERT VORHIS
Smoke Detectors 3/5/2021 Corrections Issued ROBERT VORHIS
Final 3/11/2021 Permit Finaled JOSEPH MCGARRY
Smoke Detectors 3/11/2021 Approved JOSEPH MCGARRY