9900 S VERMONT AVE 90044
Certificate Information: 9900 S VERMONT AVE 90044
- Application / Permit
- 20016-10000-03785
- Plan Check / Job No.
- B20LA02506
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Child Care Facility
- Work Description
- Change of use from existing gymnasium and kindergarden to child care facility.
- Permit Issued
- Issued on 8/26/2020
- Issuing Office
- Current Status
- CofO Issued on 2/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | AUNG SOE |
| Corrections Issued | 3/2/2020 | AUNG SOE |
| Building Plans Picked Up | 3/4/2020 | APPLICANT |
| Green Plans Picked Up | 4/8/2020 | APPLICANT |
| Quality Review Completed | 6/8/2020 | QUAN NGHIEM |
| Applicant returned to address corrections | 7/2/2020 | AUNG SOE |
| Applicant returned to address corrections | 7/7/2020 | AUNG SOE |
| Plan Check Approved | 7/13/2020 | AUNG SOE |
| Issued | 8/26/2020 | APPLICANT |
| CofO in Progress | 1/28/2022 | RUSSELL BONVOULOIR |
| CofO Issued | 2/8/2022 | TED RIES |
| Permit Finaled | 2/8/2022 | TED RIES |
Permit Application Clearance Information
| Green Code | Cleared | 4/1/2020 | AUNG SOE |
| DAS Clearance | Cleared | 4/2/2020 | SHINE LIN |
| ZA Case | Cleared | 4/9/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 4/9/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 4/9/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 4/9/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 4/9/2020 | MAXFIELD VERMY |
| Sewer availability | Cleared | 4/23/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2020 | JEANIE LAM |
| Fire Marshall Fire Life Safety | Cleared | 5/12/2020 | ANDREW KO |
| Community Plan Implem. Overlay | Cleared | 5/29/2020 | HELEN JADALI |
Contact Information
| Architect | Danielson,, C B; Lic. No.: C27307 | 3250 WILSHIRE BLVD # 1105 LOS ANGELES, CA 90010 |
| Contractor | Rbc Construction; Lic. No.: 1001190-B | 3141 TIGER RUN COURT STE 106 CARLSBAD, CA 92010 |
| Engineer | Johnson,, David D B; Lic. No.: S3032 | 7724 W 83RD ST PLAYA DEL REY, CA 90293 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/2/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 10/14/2020 | Partial Approval | JOEY BUCHANAN |
| Light Gage Steel Frame | 11/5/2020 | Partial Approval | KATY RAMIREZ |
| Insulation | 11/9/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Pre-Inspection | 11/17/2020 | Corrections Issued | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 11/23/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 11/23/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 1/5/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 1/19/2021 | Not Ready for Inspection | LANNY MERRICK |
| Structural Steel Frame | 1/19/2021 | Partial Approval | LANNY MERRICK |
| T-Bar Ceiling | 1/19/2021 | Not Ready for Inspection | LANNY MERRICK |
| Interior/Exterior Lathing | 1/25/2021 | Approved | LANNY MERRICK |
| Pre-Inspection | 3/31/2021 | Not Ready for Inspection | LANNY MERRICK |
| Light Gage Steel Frame | 6/2/2021 | Approved | LEOPOLDO MENDOZA |
| Drywall Nailing | 6/4/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 6/8/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 7/14/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 7/14/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Rough | 7/14/2021 | Approved | LEOPOLDO MENDOZA |
| Pre-Inspection | 7/14/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Reinforced Masonry Frame | 7/14/2021 | Approved | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 7/14/2021 | SGSOV Approved | LEOPOLDO MENDOZA |
| Smoke Detectors | 7/14/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 11/22/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Green Building Final | 11/22/2021 | Approved | RUSSELL BONVOULOIR |