333 S IRVING BLVD 90020

Certificate Information: 333 S IRVING BLVD 90020

Application / Permit
20016-10000-03754
Plan Check / Job No.
B20LA02492
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PARTIAL INTERIOR REMODEL OF AN EXISTING, 2-STORY, SINGLE FAMILY RESIDENCE. WORK TO INCLUDE INTERIOR DEMOLITION, REMODEL OF EXISTING KITCHEN, MASTER BATHROOM AND NEW WINDOWS AND DOOR AS INDICATED. NO CHANGE IN FLOOR AREA OR HEIGHT
Permit Issued
Issued on 8/12/2020
Issuing Office
Current Status
Permit Finaled on 2/19/2021

Permit Application Status History

Submitted 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 AUNG SOE
Corrections Issued 3/2/2020 AUNG SOE
Quality Review Completed 3/2/2020 QUAN NGHIEM
Applicant returned to address corrections 6/29/2020 AUNG SOE
Applicant returned to address corrections 7/1/2020 AUNG SOE
Plan Check Approved 7/27/2020 AUNG SOE
Building Plans Picked Up 7/28/2020 APPLICANT
Issued 8/12/2020 APPLICANT
Permit Finaled 2/18/2021 CHRIS CHRISTENSEN

Permit Application Clearance Information

HPOZ Cleared 6/2/2020 LYDIA CHAPMAN
Certificate of Compliance Cleared 6/3/2020 LAUREN PADICK

Contact Information

Architect Williams,, Noel C; Lic. No.: C33223 810 SOUTH FLOWER STREET UNIT 213      LOS ANGELES, CA 90017
Contractor Bellagio Design Build Corporation; Lic. No.: 935571-B 19336 CALVERT STREET      TARZANA, CA 91335
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/19/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 8/19/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 8/19/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 8/24/2020 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/27/2020 Not Ready for Inspection OSVALDO PARAMO
Shower Pan 8/27/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/1/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 9/21/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 9/21/2020 Approved ARTHUR SARGSYAN
Insulation 9/25/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/25/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/8/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 11/5/2020 Approved DONALD CRICHLOW
Final 2/9/2021 Partial Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 2/9/2021 SGSOV Not Ready JOSEPH MCGARRY
Final 2/18/2021 Permit Finaled CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/18/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 2/18/2021 Approved CHRIS CHRISTENSEN