1031 S BROADWAY 4TH FLOOR 90015
Certificate Information: 1031 S BROADWAY 4TH FLOOR 90015
- Application / Permit
- 20016-10000-03749
- Plan Check / Job No.
- B20LA02490
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR TENANT IMPROVEMENT TO (E) HIGH-RISE OFFICE. NEW PARTITIONS, CEILING, FINISHES AND FUNITURE.. AREA OF WORK 17,513 S.F.
- Permit Issued
- Issued on 1/6/2021
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 7/10/2024
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2020 | KEVIN MORALES |
| Corrections Issued | 2/11/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 9/8/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 9/14/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 10/23/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 10/29/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 12/8/2020 | SAMUEL GONZALEZ |
| Issued | 1/6/2021 | APPLICANT |
| Building Plans Picked Up | 1/7/2021 | APPLICANT |
| Permit Finaled | 7/10/2024 | LUIS CCAMACHO |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 3/2/2020 | GISELLE CORELLA |
| Fire Marshall Fire Life Safety | Cleared | 11/20/2020 | MENOA AGHAJANI |
Contact Information
| Architect | Wilder,, Arthur J; Lic. No.: C27915 | 3859 CARDIFF AVENUE CULVER CITY, CA 90232 |
| Contractor | Onni Contracting (California) Inc; Lic. No.: 976929-B | 315 WEST 9TH STREET #801 LOS ANGELES, CA 90015 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/19/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Final | 1/19/2021 | Off-Hour Fees Due | |
| Green Building Final | 1/19/2021 | Off-Hour Fees Due | |
| Green Building Rough | 1/19/2021 | Approved | DANIEL COLLINS |
| Light Gage Steel Frame | 1/19/2021 | Approved | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 1/19/2021 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 1/19/2021 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 1/19/2021 | Approved | DANIEL COLLINS |
| Smoke Detectors | 1/19/2021 | Off-Hour Fees Due | |
| T-Bar Ceiling | 1/19/2021 | Approved | DANIEL COLLINS |
| Final | 2/2/2021 | Partial Approval | DANIEL COLLINS |
| Green Building Final | 2/2/2021 | Approved | DANIEL COLLINS |
| Final | 6/25/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 7/10/2024 | Permit Finaled | LUIS CCAMACHO |