639 N NORTH BROADWAY 90012

Certificate Information: 639 N NORTH BROADWAY 90012

Application / Permit
20016-10000-03692
Plan Check / Job No.
B20LA02435
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE FROM RETAIL TO RESTAURANT. SCOPE TO INCLUDE NEW FLOORING, FRAMING, DRYWALL, PAINT.
Permit Issued
Issued on 2/17/2021
Issuing Office
Current Status
CofO Issued on 11/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 SAMUEL GONZALEZ
Corrections Issued 4/7/2020 SAMUEL GONZALEZ
Quality Review Completed 4/8/2020 LAWRENCE QUIRANTE
Building Plans Picked Up 4/15/2020 APPLICANT
Green Plans Picked Up 7/9/2020 APPLICANT
Plan Check Approved 12/11/2020 SAMUEL GONZALEZ
Issued 2/17/2021 APPLICANT
CofO in Progress 11/22/2023 KATY RAMIREZ
CofO Issued 11/22/2023 ERNESTO CORRAL
Permit Finaled 11/22/2023 ERNESTO CORRAL

Permit Application Clearance Information

DAS Clearance Cleared 6/29/2020 SHINE LIN
Green Code Cleared 7/6/2020 VIVIAN LAO
Sewer availability Cleared 7/10/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/16/2020 CECILIO NAVARRO
ZA Case Cleared 9/11/2020 CLAUDE GOODING
ZA Case Cleared 9/11/2020 CLAUDE GOODING
Comm Cor/Mini-Mall Cleared 9/16/2020 RONY GIRON
Redevelopment Project Area Cleared 10/23/2020 DAVID URITA
Food Service Establishment Cleared 11/5/2020 PAWAN VERMA
Food establishment approval Cleared 12/11/2020 LACDHS APPROVED
Redevelopment Project Area Cleared 2/4/2021 DAVID URITA

Contact Information

Architect Schneider,, John Christopher; Lic. No.: C31217 4881 BLUFF STREET      NORCO, CA 92860
Contractor Platinum X Construction Corp; Lic. No.: 982426-B 15791 ROCKFIELD STE C      IRVINE, CA 92618

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/12/2021 Approved LANNY MERRICK
Light Gage Steel Frame 6/29/2021 Not Ready for Inspection LANNY MERRICK
Light Gage Steel Frame 7/2/2021 Partial Approval MARK FERRARI
Drywall Nailing 7/7/2021 Partial Approval MARK FERRARI
Light Gage Steel Frame 7/30/2021 Approved JONATHAN QUACH
Drywall Nailing 8/3/2021 Approved LANNY MERRICK
Final 8/25/2023 Partial Approval JULIAN CAPUCETTI
Green Building Final 8/25/2023 Approved JULIAN CAPUCETTI
Green Building Rough 8/25/2023 Approved JULIAN CAPUCETTI
METHANE-Final 8/25/2023 Approved JULIAN CAPUCETTI
METHANE-Rough 8/25/2023 Approved JULIAN CAPUCETTI
Reinforced Masonry Frame 8/25/2023 Approved JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 8/25/2023 SGSOV Approved JULIAN CAPUCETTI
Smoke Detectors 8/25/2023 Approved JULIAN CAPUCETTI
Final 10/31/2023 Not Ready for Inspection RAFAEL CORTES
Final 11/9/2023 Partial Inspection KATY RAMIREZ
Final 11/21/2023 OK to Issue CofO KATY RAMIREZ