2039 W 80TH ST 90047
Certificate Information: 2039 W 80TH ST 90047
- Application / Permit
- 20016-10000-03686
- Plan Check / Job No.
- B20LA02431
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CHANGE EXISTING RECREATION TO ACCESSORY DWELLING UNIT, ALL WORK PER WFPP.
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- CofO Issued on 5/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2020 | RAHEL BEYENE |
| Corrections Issued | 2/7/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 5/13/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 6/22/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 9/23/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 10/14/2020 | FERNANDO FLORES |
| Issued | 10/20/2020 | APPLICANT |
| Building Plans Picked Up | 10/22/2020 | APPLICANT |
| CofO in Progress | 4/22/2021 | FREDDIE RIVERA |
| Permit Finaled | 5/8/2021 | DEROLD HAUFF |
| CofO Issued | 5/8/2021 | DEROLD HAUFF |
| Permit Finaled | 5/8/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/1/2020 | RIDWAN HARDY |
| Address approval | Cleared | 9/14/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2020 | JEANIE LAM |
| Sewer availability | Cleared | 9/14/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 11/6/2020 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 11/30/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 11/30/2020 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 11/30/2020 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/4/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/4/2020 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 12/4/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/4/2020 | Approved | FREDDIE RIVERA |
| Final | 3/10/2021 | Corrections Issued | FREDDIE RIVERA |
| Smoke Detectors | 3/10/2021 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 3/16/2021 | Approved | FREDDIE RIVERA |
| Service/Power Release | 3/16/2021 | Approved | FREDDIE RIVERA |
| Final | 4/22/2021 | OK to Issue CofO | FREDDIE RIVERA |