350 S GRAND AVE 3300 90071
Certificate Information: 350 S GRAND AVE 3300 90071
- Application / Permit
- 20016-10000-03613
- Plan Check / Job No.
- B20LA02387
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- NON-STRUCTURAL TENANT IMPROVEMENT FOR COMMERCIAL OFFICE. WORK INLCUDES MINOR INTERIOR DEMOLITION, INTERIOR PATITIONS, SUSPEND CEILINGS, AND MILLWORK. NO CHANGE IN EXISTING USE OR OCCUPANCY.
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/3/2021
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | MICHAEL LOPEZ |
| Corrections Issued | 2/6/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 2/14/2020 | SHANGQIN XIE |
| Issued | 3/6/2020 | LADBS |
| Building Plans Picked Up | 7/29/2021 | APPLICANT |
| Permit Finaled | 12/3/2021 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Fire Marshall Fire Life Safety | Cleared | 2/14/2020 | DOMINIQUE MEDINA |
Contact Information
| Architect | Koyama,, Ken; Lic. No.: C27932 | 1811 HANSCOM DRIVE SOUTH PASADENA, CA 91030 |
| Contractor | K C S West Inc; Lic. No.: 908480-B | 250 EAST 1ST STREET STE 600 LOS ANGELES, CA 90012 |
| Engineer | Bushra,, Rafeek L; Lic. No.: S4490 | 2564 W WOODLAND DR ANAHEIM, CA 92801 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 4/6/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Drywall Nailing | 4/26/2021 | Partial Approval | KATY RAMIREZ |
| Insulation | 4/28/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 5/11/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 5/13/2021 | Corrections Issued | KATY RAMIREZ |
| T-Bar Ceiling | 6/3/2021 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 7/16/2021 | Approved | KATY RAMIREZ |
| Final | 8/2/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 8/2/2021 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 8/2/2021 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 8/2/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 12/3/2021 | Permit Finaled | TIMOTHY BUXTON |
| Smoke Detectors | 12/3/2021 | Approved | TIMOTHY BUXTON |