937 N SYCAMORE AVE 90038
Certificate Information: 937 N SYCAMORE AVE 90038
- Application / Permit
- 20016-10000-03468
- Plan Check / Job No.
- B20LA02257
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Clinic
- Work Description
- CHANGE OF USE FROM SOUND STAGE PRODUCTION/OFFICE TO MEDICAL CLINIC. TENANT IMPROVEMENT FOR NEW TREATMENT ROOM AND RECEPTION AREA.
- Permit Issued
- Issued on 7/1/2020
- Issuing Office
- Current Status
- CofO Issued on 5/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | ADAM HEGAZI |
| Corrections Issued | 3/4/2020 | ADAM HEGAZI |
| Quality Review Completed | 3/7/2020 | YOUNG KIM |
| Plan Check Approved | 7/1/2020 | ADAM HEGAZI |
| Issued | 7/1/2020 | APPLICANT |
| Building Plans Picked Up | 7/10/2020 | APPLICANT |
| CofO in Progress | 5/25/2021 | TIMOTHY BUXTON |
| Permit Finaled | 5/25/2021 | ERNESTO CORRAL |
| CofO Issued | 5/25/2021 | ERNESTO CORRAL |
| Permit Finaled | 5/25/2021 | ERNESTO CORRAL |
| Green Plans Picked Up | 1/27/2023 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 4/2/2020 | SARAHI ORTEGA |
| ZI | Cleared | 4/2/2020 | SARAHI ORTEGA |
| Green Code | Cleared | 5/8/2020 | VIVIAN LAO |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2020 | WALLIE JONG |
| DAS Clearance | Cleared | 6/29/2020 | SHINE LIN |
| Sewer availability | Cleared | 6/29/2020 | WALLIE JONG |
Contact Information
| Architect | Murnane,, R Mcshane; Lic. No.: C34176 | 2898 ROWENA AVENUE UNIT 102 LOS ANGELES, CA 90039 |
| Contractor | Mallis Todd; Lic. No.: 942615-B | 43015 BLACK DEER LOOP #102 TEMECULA, CA 92590 |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/21/2020 | Approved | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 9/8/2020 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 9/8/2020 | Approved | TIMOTHY BUXTON |
| Deputy Steel/Welding | 9/14/2020 | Approved | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 9/14/2020 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 9/16/2020 | Conditional Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 10/13/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Light Gage Steel Frame | 10/29/2020 | Conditional Approval | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 10/30/2020 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 11/25/2020 | Approved | RUSSELL BONVOULOIR |
| Insulation | 12/23/2020 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 1/12/2021 | Partial Approval | TIMOTHY BUXTON |
| Final | 3/23/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 3/23/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Rough | 3/23/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| METHANE-Final | 3/23/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| METHANE-Rough | 3/23/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 3/23/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 3/23/2021 | SGSOV Not Ready | TIMOTHY BUXTON |
| Smoke Detectors | 3/23/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 3/25/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 3/25/2021 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 3/25/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Final | 3/25/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 3/25/2021 | Approved | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 3/25/2021 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 3/25/2021 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 3/25/2021 | Approved | TIMOTHY BUXTON |
| Final | 4/1/2021 | Conditional Approval | TIMOTHY BUXTON |