2030 W FAIR PARK AVE 90041
Certificate Information: 2030 W FAIR PARK AVE 90041
- Application / Permit
- 20016-10000-03379
- Plan Check / Job No.
- B20LA02201
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL SPECIAL CANTILEVER COLUMN.
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/23/2020
Permit Application Status History
| Submitted | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2020 | DANIEL SANJUAN |
| Corrections Issued | 2/20/2020 | DANIEL SANJUAN |
| Quality Review Completed | 2/23/2020 | HANS SANTIAGO |
| Plan Check Approved | 5/6/2020 | DANIEL SANJUAN |
| Issued | 5/27/2020 | LADBS |
| OK for CofC | 9/22/2020 | MARK FERRARI |
| CofC Issued | 10/23/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/12/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Ces4; Lic. No.: 1042127-B | , |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/23/2020 | Approved | MARK FERRARI |
| Wood Frame | 6/23/2020 | Partial Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 7/7/2020 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 7/7/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 7/9/2020 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 7/9/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 7/9/2020 | Approved | MARK FERRARI |
| Wood Frame | 7/9/2020 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 7/10/2020 | Conditional Approval | MARK FERRARI |
| Interior/Exterior Lathing | 7/16/2020 | Approved | MARK FERRARI |
| Final | 7/28/2020 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 7/28/2020 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 7/28/2020 | Approved | MARK FERRARI |
| Final | 9/22/2020 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/22/2020 | SGSOV Approved | MARK FERRARI |