10319 W DUNLEER DR 90064

Certificate Information: 10319 W DUNLEER DR 90064

Application / Permit
20016-10000-03272
Plan Check / Job No.
B20LA02128
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE TO DETACHED ADU PER STATE LAW GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 11/12/2020
Issuing Office
Current Status
CofO Issued on 6/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 CRYSTEL MAALOUF
Corrections Issued 4/7/2020 CRYSTEL MAALOUF
Quality Review Completed 4/7/2020 BILL STUTSMAN
Applicant returned to address corrections 5/15/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 5/19/2020 CRYSTEL MAALOUF
Green Plans Picked Up 9/1/2020 APPLICANT
Applicant returned to address corrections 9/18/2020 CRYSTEL MAALOUF
Plan Check Approved 9/22/2020 CRYSTEL MAALOUF
Issued 11/12/2020 APPLICANT
Building Plans Picked Up 11/16/2020 APPLICANT
CofO in Progress 6/1/2023 CLAYTON GRAHAM
Permit Finaled 6/7/2023 DANIEL ORRANTE
CofO Issued 6/7/2023 DANIEL ORRANTE
Permit Finaled 6/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 3/26/2020 VIVIAN LAO
Specific Plan Cleared 4/28/2020 PEDRO AYALA
Stormwater Pollution Mitigatn Cleared 5/7/2020 ORVAL HERNANDEZ-MARCI
Address approval Cleared 5/14/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 5/14/2020 DINAH GARIN
Sewer availability Cleared 5/14/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/21/2020 DINAH GARIN
Grading Pre-Inspection Cleared 8/19/2020 PATRICK MISCHLICH
GPI Written Notices Cleared 9/16/2020 CRYSTEL MAALOUF
Construction near power lines Cleared 9/17/2020 RIDWAN HARDY

Contact Information

Contractor A Clas Builders & Design Inc; Lic. No.: 770974-B 7050 OWENSMOUTH AVENUE   STE 208    CANOGA PARK, CA 91303

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/4/2020 Partial Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 2/10/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 2/10/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 2/16/2021 Partial Approval KENNETH NAGLE
Underground Mechanical 2/16/2021 Not Ready for Inspection KENNETH NAGLE
Footing/Foundation/Slab 2/24/2021 Approved KEVIN SARGSYAN
Sewer 3/1/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 4/9/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 4/9/2021 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 4/20/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 4/20/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 4/20/2021 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 4/22/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 4/22/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 7/12/2021 Approved KEVIN SARGSYAN
Green Building Rough 7/12/2021 Approved KEVIN SARGSYAN
Insulation 7/12/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/12/2021 Partial Approval KEVIN SARGSYAN
Drywall Nailing 7/21/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/21/2021 Approved KEVIN SARGSYAN
Shower Pan 7/21/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Final 5/31/2022 Corrections Issued KEVIN SARGSYAN
Final 5/31/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 5/31/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 5/31/2022 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/31/2022 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 5/31/2022 Approved KEVIN SARGSYAN
Final 5/10/2023 Corrections Issued CLAYTON GRAHAM
Final 5/17/2023 Corrections Issued CLAYTON GRAHAM
Final 5/23/2023 Corrections Issued CLAYTON GRAHAM
Final 5/31/2023 OK to Issue CofO CLAYTON GRAHAM