3696 S NORTON AVE 90018

Certificate Information: 3696 S NORTON AVE 90018

Application / Permit
20016-10000-02941
Plan Check / Job No.
B20LA01916
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE TO AN ACCESSORY DWELLING UNIT PER WFPP
Permit Issued
Issued on 2/28/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/31/2020 ADAM HEGAZI
Corrections Issued 1/31/2020 ADAM HEGAZI
Plan Check Approved 2/28/2020 SINA KHOSRAVI
Issued 2/28/2020 LADBS
CofO in Progress 4/21/2026 LUIS CASTRO
CofO Issued 4/23/2026 DEROLD HAUFF
Permit Finaled 4/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/31/2020 JEANETTE VONG
Construction near power lines Cleared 1/31/2020 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/31/2020 JEANETTE VONG
Sewer availability Cleared 1/31/2020 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/3/2020 Partial Approval COREY HUPP
PLUMBING-Rough 3/3/2020 Partial Approval COREY HUPP
PLUMBING-Rough 3/12/2020 Not Ready for Inspection COREY HUPP
Sewer 3/12/2020 Not Ready for Inspection COREY HUPP
Wood Frame 3/12/2020 Not Ready for Inspection COREY HUPP
Sewer 5/8/2020 Approved COREY HUPP
Insulation 5/12/2020 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/12/2020 Approved SABAS ALONSO
ELECTRICAL-Rough 5/14/2020 Not Ready for Inspection FREDDIE RIVERA
Gas Test 5/14/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 5/14/2020 Corrections Issued FREDDIE RIVERA
Insulation 5/14/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 5/14/2020 Not Ready for Inspection FREDDIE RIVERA
Wood Frame 5/14/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/18/2020 Approved COREY HUPP
PLUMBING-Rough 5/18/2020 Approved COREY HUPP
Underground Mechanical 5/18/2020 Approved COREY HUPP
Wood Frame 5/21/2020 Approved COREY HUPP
Drywall Nailing 5/27/2020 Approved SABAS ALONSO
Green Building Rough 5/27/2020 Approved SABAS ALONSO
Shower Pan 5/27/2020 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/10/2020 Approved COREY HUPP
Final 6/10/2020 Partial Inspection COREY HUPP
Green Building Final 6/10/2020 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 6/10/2020 SGSOV Not Ready COREY HUPP
Smoke Detectors 6/10/2020 Approved COREY HUPP
Final 6/26/2020 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 6/26/2020 SGSOV Approved COREY HUPP
Final 8/4/2020 Partial Inspection COREY HUPP
ELECTRICAL-Final 3/16/2021 Corrections Issued DAVID FEILER
Final 3/16/2021 Partial Inspection DAVID FEILER
Final 5/4/2021 Conditional Approval DAVID FEILER
Final 1/27/2022 Conditional Approval ANTHONY EGSON
HVAC-Final 1/27/2022 Approved ANTHONY EGSON
PLUMBING-Final 1/27/2022 Approved ANTHONY EGSON
Final 4/21/2026 OK to Issue CofO LUIS CASTRO