3628 S ARLINGTON AVE 90018
Certificate Information: 3628 S ARLINGTON AVE 90018
- Application / Permit
- 20016-10000-02823
- Plan Check / Job No.
- B20LA01834
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF (E) SFD. NEW WALL OPENING & REINFORCEMENT WITH BEAM & COLUMN.
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 10/16/2020
Permit Application Status History
| Submitted | 1/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | KEVIN MORALES |
| Corrections Issued | 1/30/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 2/21/2020 | SHANGQIN XIE |
| Plan Check Approved | 2/21/2020 | FERNANDO FLORES |
| Issued | 2/21/2020 | LADBS |
| Permit Finaled | 10/14/2020 | ENRIQUE PREZA |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 2/13/2020 | MAX LODER |
| Historic monument | Cleared | 2/13/2020 | MAX LODER |
Contact Information
| Contractor | L.E Construction Inc; Lic. No.: 928732-B | P O BOX 1319 GUASTI, CA 91743 |
| Engineer | Chi,, Joseph Chiwol; Lic. No.: C53156 | 19623 BOMAR CT ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/27/2020 | Not Ready for Inspection | ENRIQUE PREZA |
| Footing/Foundation/Slab | 2/27/2020 | Approved | ENRIQUE PREZA |
| BUILDING-Rough-Frame | 3/13/2020 | Approved | ENRIQUE PREZA |
| PLUMBING-Rough | 3/13/2020 | Approved | ENRIQUE PREZA |
| Insulation | 3/19/2020 | Approved | KIM BEAUCHAMP |
| Drywall Nailing | 3/31/2020 | Approved | DANIEL GONZALEZ |
| PLUMBING-Rough | 3/31/2020 | Not Ready for Inspection | DANIEL GONZALEZ |
| Shower Pan | 5/26/2020 | Approved | ENRIQUE PREZA |
| PLUMBING-Rough | 7/17/2020 | Approved | ENRIQUE PREZA |
| Insulation | 8/4/2020 | Corrections Issued | ENRIQUE PREZA |
| ELECTRICAL-Rough | 8/11/2020 | Approved | ENRIQUE PREZA |
| Insulation | 8/12/2020 | Approved | ENRIQUE PREZA |
| Drywall Nailing | 8/13/2020 | Approved | ENRIQUE PREZA |
| Interior/Exterior Lathing | 8/18/2020 | Approved | ENRIQUE PREZA |
| Special/Order Compliance | 8/31/2020 | Approved | ENRIQUE PREZA |
| Final | 9/30/2020 | Not Ready for Inspection | ENRIQUE PREZA |
| Final | 10/14/2020 | Permit Finaled | ENRIQUE PREZA |
| Smoke Detectors | 10/14/2020 | Approved | ENRIQUE PREZA |