6142 W ELEANOR AVE 90038

Certificate Information: 6142 W ELEANOR AVE 90038

Application / Permit
20016-10000-02732
Plan Check / Job No.
B20LA01752
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: USING 3 SPECIAL STEEL CANTILEVER COLUMNS WITH GRADE BEAMS AND 1 SHEAR WALL.
Permit Issued
Issued on 6/16/2020
Issuing Office
Current Status
CofC Issued on 11/12/2020

Permit Application Status History

Submitted 2/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/4/2020 DANIEL SANJUAN
Corrections Issued 3/13/2020 DANIEL SANJUAN
Quality Review Completed 3/24/2020 HANS SANTIAGO
Plan Check Approved 5/20/2020 DANIEL SANJUAN
Issued 6/16/2020 APPLICANT
OK for CofC 11/10/2020 JONATHAN QUACH
CofC Issued 11/12/2020 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 6/2/2020 MICHAEL GREGERSON

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD# 230      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 8/11/2020 Conditional Approval FRED WOHLFARTH
Pre-Inspection 8/27/2020 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 8/28/2020 Approved MARK FERRARI
Structural Steel Frame 8/28/2020 Partial Approval MARK FERRARI
Deputy Steel/Welding 9/17/2020 Conditional Approval FRED WOHLFARTH
Reinforced Concrete Frame 9/18/2020 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 9/18/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 9/18/2020 Conditional Approval MARK FERRARI
Deputy Wood Construction 9/28/2020 Conditional Approval MARK FERRARI
Reinforced Concrete Frame 10/2/2020 Approved JONATHAN QUACH
Structural Steel Frame 10/2/2020 Approved JONATHAN QUACH
Wood Frame 10/2/2020 Approved JONATHAN QUACH
Interior/Exterior Lathing 10/9/2020 Approved JONATHAN QUACH
Final 11/5/2020 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 11/5/2020 SGSOV Not Ready JONATHAN QUACH
Smoke Detectors 11/5/2020 Not Ready for Inspection JONATHAN QUACH
Final 11/6/2020 Corrections Issued JONATHAN QUACH
Final 11/10/2020 OK for CofC JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 11/10/2020 SGSOV Approved JONATHAN QUACH
Smoke Detectors 11/10/2020 Approved JONATHAN QUACH