20 E 29TH AVE 90291
Certificate Information: 20 E 29TH AVE 90291
- Application / Permit
- 20016-10000-02699
- Plan Check / Job No.
- B20LA01727
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL MOMENT FRAMES.
- Permit Issued
- Issued on 1/4/2021
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/6/2021
Permit Application Status History
| Submitted | 1/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | MANUEL MONTUFAR |
| Corrections Issued | 2/4/2020 | MANUEL MONTUFAR |
| Quality Review Completed | 2/10/2020 | HANS SANTIAGO |
| Plan Check Approved | 3/31/2020 | MANUEL MONTUFAR |
| Issued | 1/4/2021 | APPLICANT |
| OK for CofC | 10/4/2021 | GRANT WOODS |
| CofC Issued | 10/6/2021 | TED RIES |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/22/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 5104 GARDEN GROVE AVE TARZANA, CA 91356 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/11/2021 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 6/4/2021 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 6/9/2021 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 6/10/2021 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 6/10/2021 | Approved | GRANT WOODS |
| Structural Steel Frame | 6/10/2021 | Approved | GRANT WOODS |
| Wood Frame | 6/10/2021 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 6/11/2021 | Conditional Approval | GRANT WOODS |
| Interior/Exterior Lathing | 7/12/2021 | Approved | GRANT WOODS |
| Final | 9/9/2021 | Corrections Issued | GRANT WOODS |
| METHANE-Final | 9/9/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 9/9/2021 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 9/9/2021 | Approved | GRANT WOODS |
| Final | 10/4/2021 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 10/4/2021 | SGSOV Approved | GRANT WOODS |