3523 S HILLCREST DR 90016
Certificate Information: 3523 S HILLCREST DR 90016
- Application / Permit
- 20016-10000-02633
- Plan Check / Job No.
- B20LA01683
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP
- Permit Issued
- Issued on 5/1/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2020 | MONICA RAMIREZ |
| Corrections Issued | 2/3/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 4/23/2020 | RAHEL BEYENE |
| Plan Check Approved | 4/24/2020 | RAHEL BEYENE |
| Issued | 5/1/2020 | LADBS |
| Building Plans Picked Up | 5/1/2020 | APPLICANT |
| CofO in Progress | 4/4/2021 | STUART CHAPMAN |
| No Progress | 4/5/2021 | STUART CHAPMAN |
| CofO in Progress | 9/10/2021 | HORACE FULTZ |
| Permit Finaled | 9/11/2021 | DEROLD HAUFF |
| CofO Issued | 9/11/2021 | DEROLD HAUFF |
| Permit Finaled | 9/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/4/2020 | ERIK BEASLEY |
| Construction near power lines | Cleared | 4/5/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Cal-Tex Const Co; Lic. No.: 494184-B | PO BOX 1198 VENICE, CA 90294 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/13/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/13/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Underground Mechanical | 5/13/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 6/25/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 6/25/2020 | Partial Approval | COREY HUPP |
| Sewer | 6/25/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 7/6/2020 | Approved | COREY HUPP |
| PLUMBING-Rough | 7/6/2020 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2020 | Approved | COREY HUPP |
| Drywall Nailing | 7/17/2020 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 7/17/2020 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 7/21/2020 | Conditional Approval | SABAS ALONSO |
| Final | 10/13/2020 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 10/13/2020 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 10/13/2020 | Approved | DAVID FEILER |
| Final | 1/8/2021 | Corrections Issued | STUART CHAPMAN |
| Final | 1/20/2021 | Conditional Approval | STUART CHAPMAN |
| Final | 4/1/2021 | OK to Issue CofO | STUART CHAPMAN |