4686 N WOODSIDE DR 90065
Certificate Information: 4686 N WOODSIDE DR 90065
- Application / Permit
- 20016-10000-02585
- Plan Check / Job No.
- B20LA01648
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 1808 - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (8) STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 10/2/2020
- Issuing Office
- Current Status
- CofC Issued on 10/26/2021
Permit Application Status History
| Submitted | 2/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2020 | DANIEL SANJUAN |
| Corrections Issued | 3/10/2020 | DANIEL SANJUAN |
| Quality Review Completed | 3/19/2020 | HANS SANTIAGO |
| Plan Check Approved | 5/8/2020 | DANIEL SANJUAN |
| Issued | 10/2/2020 | APPLICANT |
| OK for CofC | 10/22/2021 | MARK FERRARI |
| CofC Issued | 10/26/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| HPOZ | Cleared | 4/21/2020 | TERRI OSBORNE |
| Metro Rail approval | Cleared | 5/5/2020 | ANDREW SANTIAGO |
| Tenant Habitability Plan | Cleared | 6/22/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | A R M Builders Inc; Lic. No.: 915352-B | 1080 S LA CIENEGA #311 LOS ANGELES, CA 90035 |
| Engineer | Soliman,, John; Lic. No.: NA80833 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/13/2020 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 11/30/2020 | Corrections Issued | MARK FERRARI |
| Deputy Steel/Welding | 12/3/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 12/4/2020 | Corrections Issued | MARK FERRARI |
| Deputy Reinf. Concrete | 12/9/2020 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 12/9/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Wood Construction | 1/8/2021 | Conditional Approval | MARK FERRARI |
| Wood Frame | 1/8/2021 | Partial Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Not Ready for Inspection | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 3/4/2021 | Not Ready for Inspection | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 3/9/2021 | Approved | MARK FERRARI |
| Wood Frame | 5/4/2021 | Partial Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2021 | Partial Approval | JONATHAN QUACH |
| Structural Steel Frame | 6/18/2021 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 6/18/2021 | Corrections Issued | JONATHAN QUACH |
| Drywall Nailing | 6/29/2021 | Not Ready for Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 7/1/2021 | Conditional Approval | MARK FERRARI |
| Interior/Exterior Lathing | 7/12/2021 | Partial Approval | MARK FERRARI |
| Interior/Exterior Lathing | 7/19/2021 | Corrections Issued | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 7/21/2021 | Partial Approval | MARK FERRARI |
| Final | 9/24/2021 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/24/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/24/2021 | Not Ready for Inspection | MARK FERRARI |
| Final | 10/22/2021 | Conditional Approval | MARK FERRARI |
| Smoke Detectors | 10/22/2021 | Approved | MARK FERRARI |