12409 W ARCHWOOD ST 91606
Certificate Information: 12409 W ARCHWOOD ST 91606
- Application / Permit
- 20016-10000-02583
- Plan Check / Job No.
- B20LA01646
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 1806 - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 11/18/2020
- Issuing Office
- Current Status
- CofC Issued on 3/16/2021
Permit Application Status History
| Submitted | 1/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | DANIEL YIP |
| Corrections Issued | 2/4/2020 | DANIEL YIP |
| Quality Review Completed | 2/10/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/2/2020 | DANIEL YIP |
| Plan Check Approved | 3/11/2020 | DANIEL YIP |
| Issued | 11/18/2020 | APPLICANT |
| OK for CofC | 3/4/2021 | KENNETH ROBERTS |
| CofC Issued | 3/16/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/4/2020 | WALTER RAMIREZ |
| Tenant Habitability Plan | Cleared | 11/6/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Ces4; Lic. No.: 1042127-B | , |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/23/2020 | Partial Inspection | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 1/5/2021 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 1/6/2021 | Approved | JOE VELASQUEZ |
| Footing/Foundation/Slab | 1/6/2021 | Approved | JOE VELASQUEZ |
| Light Gage Steel Frame | 1/6/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 1/6/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 1/6/2021 | Corrections Issued | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 1/7/2021 | No Access for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 1/26/2021 | Approved | JOE VELASQUEZ |
| Final | 2/2/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 2/2/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 3/4/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 3/4/2021 | Approved | KENNETH ROBERTS |