3955 S 6TH AVE 90008

Certificate Information: 3955 S 6TH AVE 90008

Application / Permit
20016-10000-02453
Plan Check / Job No.
B20LA01572
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 11/9/2020
Issuing Office
Current Status
CofO Issued on 6/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2020 APPLICANT
Assigned to Plan Check Engineer 1/28/2020 KEVIN MORALES
Corrections Issued 1/28/2020 KEVIN MORALES
Plan Check Approved 3/4/2020 FERNANDO FLORES
Issued 11/9/2020 APPLICANT
Building Plans Picked Up 11/12/2020 APPLICANT
CofO in Progress 6/23/2021 FREDDIE RIVERA
Permit Finaled 6/30/2021 DEROLD HAUFF
CofO Issued 6/30/2021 DEROLD HAUFF
Permit Finaled 6/30/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 2/28/2020 ERNEST FRESQUEZ
Address approval Cleared 3/2/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/2/2020 ELENA LOPEZ
Sewer availability Cleared 3/2/2020 ELENA LOPEZ

Contact Information

Contractor S R M General Contractors; Lic. No.: 1022126-B 827 N HOLLYWOOD WAY #178      BURBANK, CA 91505

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/17/2020 Approved FREDDIE RIVERA
Footing/Foundation/Slab 1/14/2021 Partial Approval DAVID FEILER
Footing/Foundation/Slab 1/25/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 2/5/2021 Approved FREDDIE RIVERA
Green Building Rough 2/5/2021 Approved FREDDIE RIVERA
Pre-Inspection 2/5/2021 Corrections Issued FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 2/5/2021 Approved FREDDIE RIVERA
Insulation 2/11/2021 Approved DAVID FEILER
Drywall Nailing 2/19/2021 Approved DAVID FEILER
Shower Pan 2/19/2021 Not Ready for Inspection DAVID FEILER
Interior/Exterior Lathing 2/24/2021 Approved DAVID FEILER
Shower Pan 2/24/2021 Approved DAVID FEILER
Final 6/15/2021 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Approved DAVID FEILER
Smoke Detectors 6/15/2021 Approved DAVID FEILER
Final 6/22/2021 Corrections Issued FREDDIE RIVERA
Final 6/23/2021 OK to Issue CofO FREDDIE RIVERA