400 S HOPE ST 90071
Certificate Information: 400 S HOPE ST 90071
- Application / Permit
- 20016-10000-02294
- Plan Check / Job No.
- B20LA01455
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Tenant improvement to (E) office at 11th and 12th floors (ste. 1150 and 1200). Revise breakroom and adding card readers. New partitions at elevator lobby.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 1/27/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 2/12/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 2/13/2020 | HELEN NGUYEN |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 4/5/2021 | KATY RAMIREZ |
| CofO Issued | 4/7/2021 | DAVID TSAU |
| Permit Finaled | 4/7/2021 | DAVID TSAU |
Permit Application Clearance Information
| Fire Marshall Fire Life Safety | Cleared | 2/12/2020 | PEJMAN NOORI |
Contact Information
| Architect | Gaudio,, Kristin Drews; Lic. No.: C35634 | 2008 STRONGS DRIVE VENICE, CA 90291 |
| Contractor | Warner Constructors Inc; Lic. No.: 463497-B | 6333 SAN FERNANDO ROAD GLENDALE, CA 91201 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/27/2020 | Corrections Issued | KATY RAMIREZ |
| Light Gage Steel Frame | 5/18/2020 | Partial Inspection | KATY RAMIREZ |
| Drywall Nailing | 6/3/2020 | Partial Inspection | KATY RAMIREZ |
| Final | 11/6/2020 | No Access for Inspection | KATY RAMIREZ |
| Reinforced Concrete Frame | 11/6/2020 | No Access for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 11/6/2020 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 11/6/2020 | No Access for Inspection | KATY RAMIREZ |
| Final | 2/1/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Reinforced Concrete Frame | 2/1/2021 | Approved | KATY RAMIREZ |
| Smoke Detectors | 2/1/2021 | Approved | KATY RAMIREZ |
| Final | 2/23/2021 | Partial Approval | KATY RAMIREZ |
| Final | 4/5/2021 | OK to Issue CofO | KATY RAMIREZ |