1553 1/4 E 43RD ST 90011
Certificate Information: 1553 1/4 E 43RD ST 90011
- Application / Permit
- 20016-10000-02215
- Plan Check / Job No.
- B20LA01402
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF 20' x 22' (410 SF) PORTION OF SFD TO ADU
- Permit Issued
- Issued on 3/17/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/6/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | STARR CHEN |
| Corrections Issued | 3/10/2020 | STARR CHEN |
| Quality Review Completed | 3/10/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 3/11/2020 | APPLICANT |
| Plan Check Approved | 3/17/2020 | STARR CHEN |
| Issued | 3/17/2020 | LADBS |
| CofO in Progress | 6/3/2020 | ROBERT MCDOWELL |
| Permit Finaled | 7/6/2020 | DEROLD HAUFF |
| CofO Issued | 7/6/2020 | DEROLD HAUFF |
| Permit Finaled | 7/6/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 3/11/2020 | THOMAS LANG |
| Sewer availability | Cleared | 3/11/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C90392 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/19/2020 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 3/24/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 3/25/2020 | Approved | JOAQUIN GREENOUGH |
| Insulation | 3/26/2020 | Approved | SABAS ALONSO |
| Insulation | 3/26/2020 | Off-Hour Fees Due | |
| Drywall Nailing | 3/27/2020 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/31/2020 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 3/31/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Final | 3/31/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/31/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Drywall Nailing | 4/1/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/7/2020 | No Access for Inspection | ALEJANDRO DE ARTOLA |
| Final | 4/7/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/7/2020 | No Access for Inspection | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/7/2020 | No Access for Inspection | ALEJANDRO DE ARTOLA |
| Final | 5/22/2020 | No Access for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 5/22/2020 | No Access for Inspection | ENRIQUE MIRELES |
| Final | 5/26/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Smoke Detectors | 5/26/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Drywall Nailing | 5/29/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 5/29/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 5/29/2020 | Approved | ROBERT MCDOWELL |
| Pre-Inspection | 5/29/2020 | Approved | ROBERT MCDOWELL |
| Final | 6/4/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| Smoke Detectors | 6/4/2020 | Approved | ROBERT MCDOWELL |