1810 N AVENUE 51 90042

Certificate Information: 1810 N AVENUE 51 90042

Application / Permit
20016-10000-02191
Plan Check / Job No.
B20LA01383
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
CofO Issued on 8/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Green Plans Picked Up 2/21/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 CRYSTEL MAALOUF
Corrections Issued 3/11/2020 CRYSTEL MAALOUF
Quality Review Completed 3/25/2020 BILL STUTSMAN
Applicant returned to address corrections 10/13/2021 CRYSTEL MAALOUF
Plan Check Approved 12/13/2021 CRYSTEL MAALOUF
Issued 1/18/2022 APPLICANT
Building Plans Picked Up 1/21/2022 APPLICANT
CofO in Progress 2/27/2024 CRAIG VAUGHAN
No Progress 4/25/2024 CHARLES BOGHOSKHAN
CofO in Progress 4/25/2024 CHARLES BOGHOSKHAN
CofO Issued 8/8/2024 DEROLD HAUFF
Permit Finaled 8/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/6/2021 WALLIE JONG
Address approval Cleared 7/21/2021 WALLIE JONG
Sewer availability Cleared 7/21/2021 WALLIE JONG
Green Code Cleared 12/13/2021 KHEDER ALRAZAA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/3/2022 No Access for Inspection CRAIG VAUGHAN
Final 3/3/2022 No Access for Inspection CRAIG VAUGHAN
Green Building Final 3/3/2022 No Access for Inspection CRAIG VAUGHAN
Green Building Rough 3/3/2022 No Access for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 3/3/2022 No Access for Inspection CRAIG VAUGHAN
Pre-Inspection 3/8/2022 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 5/20/2022 Corrections Issued OSVALDO PARAMO
Green Building Rough 5/20/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 5/31/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 5/31/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 6/13/2022 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 6/13/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 6/13/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 6/13/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 6/21/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 7/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 7/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 7/12/2022 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/15/2022 No Access for Inspection SCOTT FINNILA
Green Building Rough 7/15/2022 No Access for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 7/18/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/18/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 7/18/2022 Approved CRAIG VAUGHAN
HVAC-Rough 7/18/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/18/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/28/2022 Approved CHARLES BOGHOSKHAN
Insulation 7/28/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 7/28/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 8/16/2022 Approved CHARLES BOGHOSKHAN
Final 8/29/2022 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 8/29/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/29/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 8/29/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 9/2/2022 Approved CRAIG VAUGHAN
Final 9/2/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 9/2/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 9/2/2022 Approved CRAIG VAUGHAN
Smoke Detectors 9/2/2022 Approved CRAIG VAUGHAN