4142 1/2 S 5TH AVE 90008
Certificate Information: 4142 1/2 S 5TH AVE 90008
- Application / Permit
- 20016-10000-02190
- Plan Check / Job No.
- B20LA01380
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING (E) GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE # 186481
- Permit Issued
- Issued on 9/8/2020
- Issuing Office
- Current Status
- CofO Issued on 2/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2020 | RAHEL BEYENE |
| Corrections Issued | 1/24/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 2/26/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 7/1/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 8/3/2020 | STANLEY RAAP |
| Building Plans Picked Up | 8/4/2020 | APPLICANT |
| Plan Check Approved | 9/3/2020 | STANLEY RAAP |
| Issued | 9/8/2020 | APPLICANT |
| CofO in Progress | 10/28/2022 | ANTHONY EGSON |
| Permit Finaled | 2/12/2023 | DANIEL ORRANTE |
| CofO Issued | 2/12/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/12/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | THOMAS LANG |
| Sewer availability | Cleared | 2/26/2020 | THOMAS LANG |
| Construction near power lines | Cleared | 4/29/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Pro Construction Inc; Lic. No.: 1028385-B | 861 N HAMILTON BLVD POMONA, CA 91768 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 11/4/2020 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 2/23/2021 | No Access for Inspection | DAVID FEILER |
| Pre-Inspection | 2/23/2021 | No Access for Inspection | DAVID FEILER |
| Wood Frame | 2/23/2021 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 4/26/2021 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 4/26/2021 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 4/26/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 4/26/2021 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 6/9/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/15/2021 | Partial Inspection | DAVID FEILER |
| Wood Frame | 1/6/2022 | Corrections Issued | ANTHONY EGSON |
| Insulation | 2/16/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 2/24/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 9/28/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 9/28/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 9/28/2022 | Approved | ANTHONY EGSON |
| Final | 10/27/2022 | OK to Issue CofO | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Approved | ANTHONY EGSON |