1036 S MENLO AVE 90006

Certificate Information: 1036 S MENLO AVE 90006

Application / Permit
20016-10000-02039
Plan Check / Job No.
B20LA01294
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert (e) non habitable rooms to 11 accessory dwelling units to existing 49 unit apartment building per State Law
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
CofO Issued on 6/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 VU NGUYEN
Plans on Hold 2/28/2020 ALLEN MANALANSAN
Hold Released 6/9/2020 HERNAN ARREOLA
Corrections Issued 6/9/2020 VU NGUYEN
Quality Review Completed 6/30/2020 QUAN NGHIEM
Building Plans Picked Up 7/6/2020 APPLICANT
Applicant returned to address corrections 9/29/2020 VU NGUYEN
Plan Check Approved 1/26/2021 VU NGUYEN
Issued 2/3/2021 APPLICANT
CofO in Progress 6/6/2025 JEROME BLACKWOOD
Permit Finaled 6/6/2025 ERNESTO CORRAL
CofO Issued 6/6/2025 ERNESTO CORRAL
Permit Finaled 6/6/2025 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/1/2020 RENZ SORIANO
Sewer availability Cleared 9/3/2020 RENZ SORIANO
Fire Marshall Fire Life Safety Cleared 1/11/2021 MENOA AGHAJANI

Contact Information

Architect Thibodeau,, Robert E; Lic. No.: C25585 812 LINCOLN BLVD      VENICE, CA 90291
Contractor Owner-Builder       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 12/9/2021 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 2/24/2022 Partial Approval TIMOTHY BUXTON
Drywall Nailing 6/7/2023 Partial Approval NICK DANERI
Insulation 6/7/2023 Not Ready for Inspection NICK DANERI
Pre-Inspection 6/7/2023 Partial Inspection NICK DANERI
Insulation 10/5/2023 Partial Approval RICARDO ROBLES
Insulation 10/26/2023 Not Ready for Inspection JEROME BLACKWOOD
Insulation 10/27/2023 Partial Approval RICARDO ROBLES
Drywall Nailing 11/14/2023 Partial Approval JEROME BLACKWOOD
Insulation 11/14/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 12/13/2023 Partial Approval JEROME BLACKWOOD
Insulation 9/26/2024 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 10/10/2024 Partial Approval PAUL BAZERKANIAN
Insulation 3/4/2025 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 3/4/2025 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 3/4/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 3/17/2025 Partial Approval JEROME BLACKWOOD
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Partial Approval JEROME BLACKWOOD
Final 6/3/2025 OK to Issue CofO JEROME BLACKWOOD
METHANE-Final 6/3/2025 Approved JEROME BLACKWOOD
METHANE-Rough 6/3/2025 Approved JEROME BLACKWOOD
Reinforced Concrete Frame 6/3/2025 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 6/3/2025 Approved JEROME BLACKWOOD