8674 W CHALMERS DR 90035
Certificate Information: 8674 W CHALMERS DR 90035
- Application / Permit
- 20016-10000-01989
- Plan Check / Job No.
- B20LA01252
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (2) OMF
- Permit Issued
- Issued on 8/11/2020
- Issuing Office
- Current Status
- CofC Issued on 12/31/2020
Permit Application Status History
| Submitted | 1/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2020 | VARAND SARKISIAN |
| Corrections Issued | 2/20/2020 | VARAND SARKISIAN |
| Quality Review Completed | 2/24/2020 | SAI KHUM |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Plan Check Approved | 6/19/2020 | VARAND SARKISIAN |
| Issued | 8/11/2020 | APPLICANT |
| OK for CofC | 12/18/2020 | DARRYL ARNOLD |
| CofC Issued | 12/31/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 7/9/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Ariel Muller; Lic. No.: 1026822-B | 525 N FULLER AVE LOS ANGELES, CA 90036 |
| Engineer | Sagherian,, Jonathan Hovnathan; Lic. No.: C37138 | 444 PIEDMONT AVE 203 GLENDALE, CA 91206 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/12/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 9/3/2020 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 9/9/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/10/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 9/10/2020 | Corrections Issued | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 9/16/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 10/2/2020 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 10/8/2020 | Approved | DARRYL ARNOLD |
| Final | 11/18/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 11/18/2020 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/18/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 12/18/2020 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 12/18/2020 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/18/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 12/18/2020 | Approved | DARRYL ARNOLD |