821 1/2 W 41ST ST 90037
Certificate Information: 821 1/2 W 41ST ST 90037
- Application / Permit
- 20016-10000-01873
- Plan Check / Job No.
- B20LA01161
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE INTO ACCESSORY DWELLING UNIT. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- CofO Issued on 3/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 7/22/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 7/23/2020 | GEORGE ALVAREZ |
| Issued | 8/5/2020 | APPLICANT |
| Building Plans Picked Up | 8/17/2020 | APPLICANT |
| CofO in Progress | 4/21/2021 | ROBERT MCDOWELL |
| Permit Finaled | 3/17/2023 | DANIEL ORRANTE |
| CofO Issued | 3/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/26/2020 | ANACANY HURTADO |
| Community Plan Implem. Overlay | Cleared | 5/26/2020 | RAFAEL FONTES |
| ZA Case | Cleared | 5/26/2020 | ANACANY HURTADO |
| Address approval | Cleared | 6/2/2020 | JEANIE LAM |
| Sewer availability | Cleared | 6/2/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2020 | JEANIE LAM |
| Construction near power lines | Cleared | 6/12/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/12/2020 | RIDWAN HARDY |
| Redevelopment Project Area | Cleared | 6/24/2020 | GRACIELA ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/24/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 10/9/2020 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 10/9/2020 | Corrections Issued | HORACE FULTZ |
| PLUMBING-Rough | 10/9/2020 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 10/16/2020 | Corrections Issued | ROBERT MCDOWELL |
| Wood Frame | 10/16/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 10/21/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 10/21/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 10/21/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 10/21/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 10/21/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 10/29/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 10/29/2020 | Approved | ROBERT MCDOWELL |
| Final | 11/16/2020 | Corrections Issued | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Final | 11/23/2020 | Corrections Issued | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/21/2021 | Approved | ROBERT MCDOWELL |
| Final | 4/21/2021 | OK to Issue CofO | ROBERT MCDOWELL |
| HVAC-Final | 4/21/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 4/21/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 4/21/2021 | Approved | ROBERT MCDOWELL |