821 1/2 W 41ST ST 90037

Certificate Information: 821 1/2 W 41ST ST 90037

Application / Permit
20016-10000-01873
Plan Check / Job No.
B20LA01161
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE INTO ACCESSORY DWELLING UNIT. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 8/5/2020
Issuing Office
Current Status
CofO Issued on 3/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 7/22/2020 GEORGE ALVAREZ
Plan Check Approved 7/23/2020 GEORGE ALVAREZ
Issued 8/5/2020 APPLICANT
Building Plans Picked Up 8/17/2020 APPLICANT
CofO in Progress 4/21/2021 ROBERT MCDOWELL
Permit Finaled 3/17/2023 DANIEL ORRANTE
CofO Issued 3/17/2023 DANIEL ORRANTE
Permit Finaled 3/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

"Q" conditions Cleared 5/26/2020 ANACANY HURTADO
Community Plan Implem. Overlay Cleared 5/26/2020 RAFAEL FONTES
ZA Case Cleared 5/26/2020 ANACANY HURTADO
Address approval Cleared 6/2/2020 JEANIE LAM
Sewer availability Cleared 6/2/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/11/2020 JEANIE LAM
Construction near power lines Cleared 6/12/2020 RIDWAN HARDY
Construction within easement Cleared 6/12/2020 RIDWAN HARDY
Redevelopment Project Area Cleared 6/24/2020 GRACIELA ACOSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/24/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 10/9/2020 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Rough 10/9/2020 Corrections Issued HORACE FULTZ
PLUMBING-Rough 10/9/2020 Approved HORACE FULTZ
ELECTRICAL-Final 10/16/2020 Corrections Issued ROBERT MCDOWELL
Wood Frame 10/16/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 10/21/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 10/21/2020 Approved ROBERT MCDOWELL
Insulation 10/21/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 10/21/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 10/21/2020 Approved ROBERT MCDOWELL
Drywall Nailing 10/29/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 10/29/2020 Approved ROBERT MCDOWELL
Final 11/16/2020 Corrections Issued ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Not Ready ROBERT MCDOWELL
Final 11/23/2020 Corrections Issued ROBERT MCDOWELL
ELECTRICAL-Final 4/21/2021 Approved ROBERT MCDOWELL
Final 4/21/2021 OK to Issue CofO ROBERT MCDOWELL
HVAC-Final 4/21/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 4/21/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 4/21/2021 Approved ROBERT MCDOWELL