16633 W SCHOENBORN ST 91343
Certificate Information: 16633 W SCHOENBORN ST 91343
- Application / Permit
- 20016-10000-01810
- Plan Check / Job No.
- B20LA01114
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- EV EQUIPMENT MOUNTING FOR BTC CHARGING DISPENSERS (20)
- Permit Issued
- Issued on 8/4/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/29/2021
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 3/3/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 3/5/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 3/9/2020 | APPLICANT |
| Plan Check Approved | 4/14/2020 | SAMUEL GONZALEZ |
| Issued | 8/4/2020 | APPLICANT |
| Permit Finaled | 4/29/2021 | JEFFREY FULTON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Engineer | Zacher,, Paul K; Lic. No.: S3878 | 1478 STONE PT DR 190 ROSEVILLE, CA 95661 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 10/21/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 10/21/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 10/28/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 10/28/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 10/28/2020 | Approved | JEFFREY FULTON |
| Final | 11/15/2020 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 11/15/2020 | Off-Hour Fees Due | |
| Special/Order Compliance | 11/15/2020 | Off-Hour Fees Due | |
| Final | 11/16/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Final | 1/29/2021 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 1/29/2021 | SGSOV Not Ready | JEFFREY FULTON |
| Final | 4/29/2021 | Permit Finaled | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 4/29/2021 | SGSOV Approved | JEFFREY FULTON |