423 S WESTERN AVE 90020
Certificate Information: 423 S WESTERN AVE 90020
- Application / Permit
- 20016-10000-01795
- Plan Check / Job No.
- B20LA01101
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Night Club
- Work Description
- CHANGE OF USE FROM (E) RESTAURANT AND BAR TO (N) KARAOKE ROOMS
- Permit Issued
- Issued on 6/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/6/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | ZAW HAN |
| Corrections Issued | 2/24/2020 | ZAW HAN |
| Quality Review Completed | 3/13/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 3/13/2020 | APPLICANT |
| Applicant returned to address corrections | 6/2/2020 | ZAW HAN |
| Plan Check Approved | 6/4/2020 | ZAW HAN |
| Issued | 6/16/2020 | LADBS |
| CofO in Progress | 10/28/2020 | TIMOTHY BUXTON |
| CofO Issued | 11/6/2020 | ERNESTO CORRAL |
| Permit Finaled | 11/6/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 2/25/2020 | EMIL KYUPELYAN |
| ZA Case | Cleared | 3/10/2020 | JOE LUCKEY |
| DAS Clearance | Cleared | 3/19/2020 | WAI LAU |
| Redevelopment Project Area | Cleared | 4/3/2020 | GRACIELA ACOSTA |
| Fire Marshall Fire Life Safety | Cleared | 5/14/2020 | ANDREW KO |
Contact Information
| Contractor | Invent Contractor Inc; Lic. No.: 1017922-B | 2100 W WASHINGTON BLVD #2 LOS ANGELES, CA 90018 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/8/2020 | Approved | TIMOTHY BUXTON |
| Insulation | 7/10/2020 | Partial Inspection | JONATHAN QUACH |
| Insulation | 7/14/2020 | Approved | JONATHAN QUACH |
| Drywall Nailing | 7/20/2020 | Approved | JONATHAN QUACH |
| Light Gage Steel Frame | 9/9/2020 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 9/9/2020 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 9/9/2020 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 9/9/2020 | Approved | TIMOTHY BUXTON |
| Final | 9/23/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Wood Frame | 9/23/2020 | Approved | TIMOTHY BUXTON |
| Final | 10/6/2020 | Conditional Approval | TIMOTHY BUXTON |
| Final | 10/28/2020 | OK to Issue CofO | TIMOTHY BUXTON |