13111 W VANOWEN ST 91605
Certificate Information: 13111 W VANOWEN ST 91605
- Application / Permit
- 20016-10000-01786
- Plan Check / Job No.
- B20LA01095
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 1750 -Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 12/24/2020
- Issuing Office
- Current Status
- CofC Issued on 10/18/2021
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2020 | DANIEL YIP |
| Corrections Issued | 2/4/2020 | DANIEL YIP |
| Quality Review Completed | 2/11/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/2/2020 | DANIEL YIP |
| Applicant returned to address corrections | 3/10/2020 | DANIEL YIP |
| Plan Check Approved | 3/20/2020 | DANIEL YIP |
| Issued | 12/24/2020 | APPLICANT |
| OK for CofC | 7/21/2021 | JOE VELASQUEZ |
| CofC Issued | 10/18/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/2/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/8/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 3/30/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 3/30/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 4/7/2021 | Corrections Issued | JOE VELASQUEZ |
| Wood Frame | 4/7/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 4/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 4/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 4/16/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 4/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Insulation | 4/21/2021 | Partial Approval | JOE VELASQUEZ |
| Wood Frame | 4/21/2021 | Corrections Issued | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 6/4/2021 | Approved | JONATHAN QUACH |
| Final | 7/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/9/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 7/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 7/21/2021 | OK for CofC | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/21/2021 | SGSOV Approved | JOE VELASQUEZ |
| Smoke Detectors | 7/21/2021 | Approved | JOE VELASQUEZ |