127 W 31ST ST 90007

Certificate Information: 127 W 31ST ST 90007

Application / Permit
20016-10000-01422
Plan Check / Job No.
B20LA00885
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
FIRE DAMAGE REPAIR ON ROOF FRAMING. NEW RAMP FOR 127 W 31ST ST UNIT. UPGRADE ACCESSIBILITY FOR ALL BATHS. CHANGE OF USE FROM ADULT DAY CARE TO OFFICE ALL UNITS.
Permit Issued
Issued on 9/15/2020
Issuing Office
Current Status
CofO Issued on 9/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/24/2020 GEORGE ALVAREZ
Corrections Issued 1/30/2020 GEORGE ALVAREZ
Applicant returned to address corrections 4/21/2020 GEORGE ALVAREZ
Plan Check Approved 5/29/2020 GEORGE ALVAREZ
Issued 9/15/2020 APPLICANT
Building Plans Picked Up 9/17/2020 APPLICANT
CofO in Progress 8/24/2021 LEOPOLDO MENDOZA
CofO in Progress 8/24/2021 LEOPOLDO MENDOZA
CofO Issued 9/7/2021 DAVID TSAU
Permit Finaled 9/7/2021 DAVID TSAU

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 2/6/2020 TERRI OSBORNE
Roof/Waste drainage to street Cleared 2/6/2020 JEANIE LAM
Redevelopment Project Area Cleared 4/6/2020 DAVID URITA
Encroachment in public way Cleared 4/10/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 5/7/2020 ELAINE LEI
Sewer availability Cleared 5/7/2020 ELAINE LEI

Contact Information

Contractor Macco Construction Inc; Lic. No.: 793557-B 4833 SAN MARCOS PLACE      LOS ANGELES, CA 90042
Engineer Vega,, Cayetano Gonzalez; Lic. No.: C43117 9234 STAMPS AVE      DOWNEY, CA 90240

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2020 Partial Inspection LEOPOLDO MENDOZA
Pre-Inspection 12/4/2020 Partial Approval LEOPOLDO MENDOZA
Wood Frame 12/15/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 1/20/2021 Not Ready for Inspection LANNY MERRICK
Wood Frame 1/27/2021 Approved RUSSELL BONVOULOIR
Drywall Nailing 2/2/2021 Approved LANNY MERRICK
Deputy Drilled-In Anchors 2/4/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 2/5/2021 Approved LANNY MERRICK
Wood Frame 2/18/2021 Approved LANNY MERRICK
Drywall Nailing 2/26/2021 Approved LANNY MERRICK
Interior/Exterior Lathing 2/26/2021 Approved LANNY MERRICK
Pre-Inspection 4/13/2021 Not Ready for Inspection LANNY MERRICK
Pre-Inspection 4/14/2021 Corrections Issued LANNY MERRICK
Final 7/30/2021 Not Ready for Inspection LEOPOLDO MENDOZA
METHANE-Final 7/30/2021 Approved LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 7/30/2021 SGSOV No Gas LEOPOLDO MENDOZA
Smoke Detectors 7/30/2021 Approved LEOPOLDO MENDOZA
Final 8/12/2021 OK to Issue CofO LEOPOLDO MENDOZA