127 W 31ST ST 90007
Certificate Information: 127 W 31ST ST 90007
- Application / Permit
- 20016-10000-01422
- Plan Check / Job No.
- B20LA00885
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- FIRE DAMAGE REPAIR ON ROOF FRAMING. NEW RAMP FOR 127 W 31ST ST UNIT. UPGRADE ACCESSIBILITY FOR ALL BATHS. CHANGE OF USE FROM ADULT DAY CARE TO OFFICE ALL UNITS.
- Permit Issued
- Issued on 9/15/2020
- Issuing Office
- Current Status
- CofO Issued on 9/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2020 | GEORGE ALVAREZ |
| Corrections Issued | 1/30/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 4/21/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 5/29/2020 | GEORGE ALVAREZ |
| Issued | 9/15/2020 | APPLICANT |
| Building Plans Picked Up | 9/17/2020 | APPLICANT |
| CofO in Progress | 8/24/2021 | LEOPOLDO MENDOZA |
| CofO in Progress | 8/24/2021 | LEOPOLDO MENDOZA |
| CofO Issued | 9/7/2021 | DAVID TSAU |
| Permit Finaled | 9/7/2021 | DAVID TSAU |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 2/6/2020 | TERRI OSBORNE |
| Roof/Waste drainage to street | Cleared | 2/6/2020 | JEANIE LAM |
| Redevelopment Project Area | Cleared | 4/6/2020 | DAVID URITA |
| Encroachment in public way | Cleared | 4/10/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2020 | ELAINE LEI |
| Sewer availability | Cleared | 5/7/2020 | ELAINE LEI |
Contact Information
| Contractor | Macco Construction Inc; Lic. No.: 793557-B | 4833 SAN MARCOS PLACE LOS ANGELES, CA 90042 |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: C43117 | 9234 STAMPS AVE DOWNEY, CA 90240 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/6/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 12/4/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Wood Frame | 12/15/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 1/20/2021 | Not Ready for Inspection | LANNY MERRICK |
| Wood Frame | 1/27/2021 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 2/2/2021 | Approved | LANNY MERRICK |
| Deputy Drilled-In Anchors | 2/4/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 2/5/2021 | Approved | LANNY MERRICK |
| Wood Frame | 2/18/2021 | Approved | LANNY MERRICK |
| Drywall Nailing | 2/26/2021 | Approved | LANNY MERRICK |
| Interior/Exterior Lathing | 2/26/2021 | Approved | LANNY MERRICK |
| Pre-Inspection | 4/13/2021 | Not Ready for Inspection | LANNY MERRICK |
| Pre-Inspection | 4/14/2021 | Corrections Issued | LANNY MERRICK |
| Final | 7/30/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| METHANE-Final | 7/30/2021 | Approved | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2021 | SGSOV No Gas | LEOPOLDO MENDOZA |
| Smoke Detectors | 7/30/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 8/12/2021 | OK to Issue CofO | LEOPOLDO MENDOZA |