18422 W NAPA ST 91325
Certificate Information: 18422 W NAPA ST 91325
- Application / Permit
- 20016-10000-01405
- Plan Check / Job No.
- B20LA00876
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install (2) Steel Special Cantilever Columns and Shear wall
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 3/17/2021
Permit Application Status History
| Submitted | 1/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2020 | THOMAS SHERMAN |
| Corrections Issued | 1/27/2020 | THOMAS SHERMAN |
| Quality Review Completed | 1/27/2020 | HANS SANTIAGO |
| Plan Check Approved | 2/14/2020 | THOMAS SHERMAN |
| Issued | 5/27/2020 | LADBS |
| OK for CofC | 9/22/2020 | DANIEL VARNUM |
| CofC Issued | 3/17/2021 | DAVID TSAU |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/3/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Ces4; Lic. No.: 1042127-B | , |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/30/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 8/14/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 8/21/2020 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 8/21/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 8/21/2020 | Approved | DANIEL VARNUM |
| Wall Anchors | 8/21/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 8/21/2020 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 8/27/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 8/27/2020 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 9/9/2020 | Approved | DANIEL VARNUM |
| Final | 9/18/2020 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 9/18/2020 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 9/18/2020 | Approved | DANIEL VARNUM |
| Final | 9/22/2020 | OK for CofC | DANIEL VARNUM |